PROJECT FEASIBILITY REPORT OF DYEING UNIT OF INTERSTOFF CLOTHING LIMITED GULSHAN, DHAKA.

INTRODUCTION

The company has existing Woven & Knit Garments, Knitting-Knit Dyeing & Other related Industries and exporting Garments for last 10 years to Europe, USA & Canada successfully.
School Dress is one of the major exporting items which requires T.C. 65/35 dyed fabric and depends on imported Dyed/Finished fabrics. It requires about 40000 yds. every day.

The management feels to set-up own production units considering the following :
(a) Export to Europe can attract GSP benefit up to 12% on FOB value of the Garments if the garments are produced from locally produced fabric.
(b) Buyer’s productivity – currently lead time for …show more content…

Assume that for Gas connection 4” dia gas line is to be drawn from main line and for this purpose L.S. Tk.20 lac has been estimated. Total cost of land including development cost stands at Tk. 170 lac. Detailed particulars of land are in Annexure ….

Building and Civil works :

The building and civil works of the project will include main factory building, maintenance room, laboratory, Office room, raw materials & finished goods godown, store room, generator, boiler house, pump house, security guard rooms, time office, toilet, prayer room, canteen, administrative building, security barrack etc. Total estimated covered area of the building are of 54200 sft. where main factory building is 25000 sft.

The main building will be made of re-inforced frame structure with r.c.c. roof, brick masonry walls, cemented floor, doors, windows etc. In addition, boundary wall, drainage, car parking etc. will need.

Civil Construction

Boundary Wall ; Considering Foundation, 1 Great Beam ( GB), 2 Linter, 6’ height, 3’ Barbed wire, cost of the boundary wall for 2.00 acre of newly purchased land will be about Periphery 240x2+360x2 = 1200 rft x Tk.200 = Tk.2,40,000

Factory Building

The construction work for factory building considered as 25000 sft. 24’ height with iron Tuss roof & cost comes about Tk.1,37,50,000.

Steam, Water and Gas pipe Line
The proposed machinery will require steam, water & Gas connection. So