1. Draw a Gantt Chart for the following Activities 2. Draw Critical Path Method Chart for the following Activities

Residential Construction Academy: House Wiring (MindTap Course List)
4th Edition
ISBN:9781285852225
Author:Gregory W Fletcher
Publisher:Gregory W Fletcher
Chapter1: Residential Workplace Safety
Section: Chapter Questions
Problem 25RQ
icon
Related questions
Question

Engineering Management

Follows
Weeks
Task
Task Description
Manning level
Task
(duration)
Start
Site Clearing
A
1.0
3
Start
0.6
Obtain Lumber and basic materials
1
Start
2.0
Obtain other materials and components
1
D
B
2.0
Prefabricate wall panels
4
B
0.9
Prefabricate roof trusses
3
F
А, В
1.0
Form and pour footings and floor slab
3
G
D, F
0.3
Erect with Panels
4
H
E, G
0.2
Erect Roof Trusses
4
C, H
0.5
Complete Roof
3
2.0
Finish Interior
4
L
1.0
Finish Exterior
2
M
0.4
Clean up site
1
К, М
0.2
Final Inspection and Acceptance
1
Transcribed Image Text:Follows Weeks Task Task Description Manning level Task (duration) Start Site Clearing A 1.0 3 Start 0.6 Obtain Lumber and basic materials 1 Start 2.0 Obtain other materials and components 1 D B 2.0 Prefabricate wall panels 4 B 0.9 Prefabricate roof trusses 3 F А, В 1.0 Form and pour footings and floor slab 3 G D, F 0.3 Erect with Panels 4 H E, G 0.2 Erect Roof Trusses 4 C, H 0.5 Complete Roof 3 2.0 Finish Interior 4 L 1.0 Finish Exterior 2 M 0.4 Clean up site 1 К, М 0.2 Final Inspection and Acceptance 1
1. Draw a Gantt Chart for the following Activities
2. Draw Critical Path Method Chart for the following Activities
Transcribed Image Text:1. Draw a Gantt Chart for the following Activities 2. Draw Critical Path Method Chart for the following Activities