2. AG Construction enters into a contract with a customer to build a new headquarters facility for $1,000,000 on January 1, 2023 with a performance bonus of $100,000 if the building is completed by July 31, 2023. The bonus is reduced by $20,000 each week that completion is delayed. AG commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by Probability July 31, 2023 65% August 7, 2023 25% August 14, 2023 5% August 21, 2023 5% a. Calculate the contract price for AG using the probability-weighted (expected value) method. b. Assume that AG can only determine the probabilities of completing the project by July 31 (65%) or not meeting the deadline (35%). Calculate the contract price under this scenario.

Financial Accounting Intro Concepts Meth/Uses
14th Edition
ISBN:9781285595047
Author:Weil
Publisher:Weil
Chapter8: Revenue Recognition, Receivables, And Advances From Customers
Section: Chapter Questions
Problem 48P
icon
Related questions
Question

Qw.149.

2. AG Construction enters into a contract with a customer to build a new
headquarters facility for $1,000,000 on January 1, 2023 with a performance
bonus of $100,000 if the building is completed by July 31, 2023. The bonus is
reduced by $20,000 each week that completion is delayed. AG commonly
includes these completion bonuses in its contracts and, based on prior
experience, estimates the following completion outcomes:
Completed by Probability July 31, 2023 65% August 7, 2023 25% August 14,
2023 5% August 21, 2023 5%
a. Calculate the contract price for AG using the probability-weighted
(expected value) method.
b. Assume that AG can only determine the probabilities of completing the
project by July 31 (65%) or not meeting the deadline (35%). Calculate the
contract price under this scenario.
Transcribed Image Text:2. AG Construction enters into a contract with a customer to build a new headquarters facility for $1,000,000 on January 1, 2023 with a performance bonus of $100,000 if the building is completed by July 31, 2023. The bonus is reduced by $20,000 each week that completion is delayed. AG commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by Probability July 31, 2023 65% August 7, 2023 25% August 14, 2023 5% August 21, 2023 5% a. Calculate the contract price for AG using the probability-weighted (expected value) method. b. Assume that AG can only determine the probabilities of completing the project by July 31 (65%) or not meeting the deadline (35%). Calculate the contract price under this scenario.
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Financial Accounting Intro Concepts Meth/Uses
Financial Accounting Intro Concepts Meth/Uses
Finance
ISBN:
9781285595047
Author:
Weil
Publisher:
Cengage
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
SWFT Comprehensive Vol 2020
SWFT Comprehensive Vol 2020
Accounting
ISBN:
9780357391723
Author:
Maloney
Publisher:
Cengage
Individual Income Taxes
Individual Income Taxes
Accounting
ISBN:
9780357109731
Author:
Hoffman
Publisher:
CENGAGE LEARNING - CONSIGNMENT
SWFT Comprehensive Volume 2019
SWFT Comprehensive Volume 2019
Accounting
ISBN:
9780357233306
Author:
Maloney
Publisher:
Cengage
SWFT Individual Income Taxes
SWFT Individual Income Taxes
Accounting
ISBN:
9780357391365
Author:
YOUNG
Publisher:
Cengage