3. When planning a festival, the program cannot be printed before the key artists are committed. Which precedence relationship best describes the relationship between "get artists' commitment" and "print program"?   a. Start-to-Start b. Start-to-Finish c. Finish-to-Finish d. Finish-to-Start

Information Technology Project Management
9th Edition
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Kathy Schwalbe
Chapter5: Project Scope Management
Section: Chapter Questions
Problem 5E
icon
Related questions
Question
100%

 

3. When planning a festival, the program cannot be printed before the key artists are committed. Which precedence relationship best describes the relationship between "get artists' commitment" and "print program"?

 

a. Start-to-Start

b. Start-to-Finish

c. Finish-to-Finish

d. Finish-to-Start

 

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Module hierarchy chart
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Information Technology Project Management
Information Technology Project Management
Computer Science
ISBN:
9781337101356
Author:
Kathy Schwalbe
Publisher:
Cengage Learning