4. If the sum of the variance of the activities on the critical path is equal to 25 weeks and the expected project completion time is 65 weeks. What is the probability that the project will take less than 70 weeks for completion? a. 2.5% b. 8% c. 16% d. 84% e. 99.7% 5. Using the same data as in Q. 4, what is the probability that the project will take more than 75 weeks? I a. 2.5% b. 16% c. 34% d. 50% e. 97.5%
4. If the sum of the variance of the activities on the critical path is equal to 25 weeks and the expected project completion time is 65 weeks. What is the probability that the project will take less than 70 weeks for completion? a. 2.5% b. 8% c. 16% d. 84% e. 99.7% 5. Using the same data as in Q. 4, what is the probability that the project will take more than 75 weeks? I a. 2.5% b. 16% c. 34% d. 50% e. 97.5%
A First Course in Probability (10th Edition)
10th Edition
ISBN:9780134753119
Author:Sheldon Ross
Publisher:Sheldon Ross
Chapter1: Combinatorial Analysis
Section: Chapter Questions
Problem 1.1P: a. How many different 7-place license plates are possible if the first 2 places are for letters and...
Related questions
Question
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 1 images
Recommended textbooks for you
A First Course in Probability (10th Edition)
Probability
ISBN:
9780134753119
Author:
Sheldon Ross
Publisher:
PEARSON
A First Course in Probability (10th Edition)
Probability
ISBN:
9780134753119
Author:
Sheldon Ross
Publisher:
PEARSON