6. From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take? D ABCDE ID Description Survey site Excavate site Install power lines Install drainage Pour foundation Predecessor None A IBB C, D Time 24353
Q: You work for B&B Import and Export Incorporated, who just acquired a new business, Agro Smart…
A: Below is the road map to success from an operations management and supply chain perspective:…
Q: Q4/ Company produced 1000 pieces of air conditioners per year, the order cost is 6000$, the shortage…
A:
Q: provide a list of characteristics that stand out in well-thought-out service delivery systems.
A: Some of the characteristics that must be present in the well-thought-out service delivery system are…
Q: The MPS start quantities for products A and B are given as follows: Product A B Product A B 1 2 20…
A: Given that, There are 2 products A and B For product A, For WS 200:Setup time = 0.25Processing time…
Q: Audi is considering three locations A, B and C for the production of its new model SUV XL500. The…
A: Total cost crossover point will helps to identify the suitable level production units. A crossover…
Q: File n Paste Clipboard F1 1 2 3 4 AutoSave on 14 15 16 17 18 19 20 21 22 23 A Task 2 of 26 Workshop…
A: Given Excel sheet-
Q: Question 1 A paint manufacturer uses 3,200 liters of chemicals a year. Currently the firm purchases…
A: Given data is Annual demand (D) = 3200 liters Purchase cost (P) = $3 per liter Order cost (S) = $100…
Q: Q3- Define vertical storage and horizontal storage? What is effective for FMCG versus Industrial…
A: An industry is a distinct set of businesses that participate in comparable commercial activities,…
Q: PLEASE GIVE THE PLAN OF ACTION AND EVALUATION CONTRO. Office Depot has almost 1,000 office…
A: Plan of Action: Increase Marketing efforts: Office Depot should develop a targeted marketing…
Q: You have just graduated from college and are looking to buy your first car. Money is tight right…
A: Given, Importance to you is a column like weight to the preferred dimension. The greatest value can…
Q: 15. The Goodparts Company produces a component that is subsequently used in the aero- space…
A: Bottleneck resource is the resource which has the least capacityProcess Capacity=Capacity of the…
Q: How does the MRP system handle information in detail?
A: MRP is used by businesses to plan production and delivery, keep track of inventory levels, and…
Q: Oliver County Cars (OCC) is a large custom made car store located in Oliver County, New York. OCC…
A: The minimal length of time that must elapse between orders for a product in order to reduce the…
Q: Analyse what are the future necessities in the field of SCM4.0 applied to sustainable supply chain…
A: Supply chain management 4.0 means a technology and digitalization-driven supply chain which will…
Q: The Attaran Corporation manufactures two electrical products: portable air conditioners and portable…
A: Given, X = number of air conditioners to be produced Y = number of heaters to be produced Objective…
Q: Imagine you work for a breakfast cereal company that makes prepared products that are served cold.…
A: Now, we want to understand the product's initial demand. The methods for anticipating demand can…
Q: Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor…
A: Estimated time (Te) = (a+4×m+b)6Variance (σ2) = (b-a)236
Q: Answer the following question. What is Operational Research? What are the applications of…
A: The term "operations research," more commonly abbreviated as "OR," refers to a mathematical or…
Q: Using the following data, calculate X and S charts Sample X1 2 3 4 5 6 0.078 0.082 0.102 0.079 0.085…
A: Given-
Q: Case Study 2: Quality Management Your line manager has become increasingly concerned about the…
A: A p chart is used when observations can be placed into yes/no category decisions such as good or…
Q: Q1. A company must respond to the requirements of the customer. For this purpose, 2.000 unit of…
A: Find the Calculation methods below: Single Server: The probability that zero customers in the system…
Q: what type of manufacturing process did LWT appear to be using? What level of customization was it…
A: “Since you have posted multiple questions, we will provide the solution only to the first question…
Q: A project with total budget cost of 30 cr. is scheduled to be completed in 80 weeks. A periodic…
A: Given- Budgeted cost of work performed = 17 cr.Actual cost of work performed = 19 cr.Budgeted cost…
Q: When a security breach happens, how should firms respond?
A: Data breaches are a genuine danger for small organizations, even with the finest security safeguards…
Q: roject Managemet 7. Discuss and demonstrate the Project Life Cycle for a typical project…
A: Every project, program, and product have a unique project life cycle with distinct development…
Q: REQUIREMENTS: a) Formulate the appropriate linear programming model for this problem. b) Develop the…
A: Here, For the given data set, I would formulate the LP, First, I would identify the decision…
Q: A decision-making process can determine the success or failure of an organization, and how well it…
A: ANSWER : In my organization I used to be given task of developing the Feature Flag Service. I could…
Q: Speed of missiles. Deluxe model has an accuracy of plus or minus 2 km per hour, whereas standard…
A: Linear Programming is a mathematical and statistical tool that is used in operations management to…
Q: If today stock is trading for $60 a share. You are confident that the stock price will experience a…
A: ANSWER : XYZ Inc’s stock is trading for $60 per share. You are confident that stock price of the XYZ…
Q: Start date: April 8, 2022 Working days: Monday-Saturday Assume no holidays. What is the project…
A: For the outreach program, various activities are mentioned with descriptions and the immediate…
Q: Agan Interior Design provides home and office decorating assistance to its customers. In normal…
A: Given- Arrival time = 2.1 customer per hrService time for 1 consultant = 8 minutes per…
Q: (M/M/s/K Model). Leia is responsible for 13 data units in the IT offices in a small business called…
A: Queuing theory is a part of operations management. It is dependent on factors like arrival rate,…
Q: 1) The Primo Insurance Company is introducing two new product lines: special risk insurance and…
A: Decision Variable: Suppose-x1 be the no. of product lines of special risk insurancex2 be the no. of…
Q: ) How much revenue has Tesco generated overall over the last recorded five years? Write the formula…
A: We are given a table of Tesco revenue by location between 2018 and 2022. Now, we have to write down…
Q: Why is it important to create an outline as oppesed to simply writing a rough draft? Why is the…
A: Planning aids an organization in determining the best course for achieving its objectives. Reviewing…
Q: TASK: 1. identification of problem, give more long explanation/details 2. swot analysis, give more…
A: Bureaucracy can be defined as to a complex organization that multilayer the systems and processes.…
Q: Give ONE (1) example of a loss exposures that might be encountered by the following risks i. Loss…
A: There can be many risks that affect the business and overall productivity. These losses affect the…
Q: What TOC method could be used to relieve or improve workflow
A: Theory of Constraints is a system-based philosophy which states that the constraint in a system…
Q: Q2/ Mobile shop produced 600 pieces of mobile phone per year, the order cost is 2000S, the shortage…
A:
Q: Understanding the security risks can equip the hospital administrator to direct and monitor the…
A: Many internal and external security concerns, such as the manipulation and theft of sensitive…
Q: 3. A batch of exported goods of 400 cases, 50 kg, 60 x 40 x 30CM per case, were shipped from Tianjin…
A: Given that, The number of cases exported = 400 casesThe dimensions of the case = 50kg, 60×40×30cm…
Q: 1. How do managerial skills differ from entrepreneurial skills? When would an entrepreneur's skills…
A: ANSWER : Managerial skills refer to the abilities and knowledge needed to effectively manage and…
Q: The owner of Eat Now Restaurant implemented an expanded menu early last year. The menu was a…
A: ANSWER : The mass customization is a technique of specially made wherein base item is made in…
Q: Number of standard bags produced per week = 360 (enter your response as a whole number).…
A: Here, there are two decision variables, The number of standard bags=X1 and the number of deluxe…
Q: What elements would be important to put in setting up a CQI plan at the beginning of program…
A: A CQI strategy is a company's road map for enhancing its capabilities, outputs, processes, and…
Q: What are the benefits of choosing to implement Agile inside the organization?
A: Agile organization is a type of organization where employees work cross functionally and have more…
Q: The five risk management approaches should be listed and briefly defined.
A: Risk management refers to handling and controlling the risks associated with a project or company in…
Q: Your company had been shortlisted on tinder and you had been assigned as the lead negotiator, the…
A: As the lead negotiator for my company, I have been assigned to negotiate a deal with the buyer who…
Q: state argument for and against the following statements: there are other things more valuable in an…
A: Human capital is the information, abilities, or health that individuals invest in and collect…
Q: Achieving success requires a strong network, high profile, collaborative effort, and punctual…
A: Supply Chain Technology The supply chain technology are boosting the efficiency of the supply chain…
From the following information, develop an AON project network. Complete the
forward and backward pass, compute activity slack, and identify the critical path.
How many days will the project take?
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 3 images
- Given the following information, a. Draw a project network. b. Complete the forward and backward pass, compute activity slack, and identify the critical path. c. How sensitive is the network schedule? Briefly justify your answer? d. Which activities have free slack? Activity Predecessor Duration (days) A None 10 B None 20 C A 10 D A 30 E B 10 F C 30 G C, D 20 H D, E 10 I F, G, H 20You are creating a customer database for the Hillsboro Hops minor league baseball team. Draw a project network given the information in the table that follows. Complete the forward and backward pass, compute activity slack, and identify the critical path. How long will this project take? How sensitive is the network schedule? Calcu-late the free slack and total slack for all noncritical activities.ID Description Predecessor Time (days)A Systems design None 2 B Subsystem A design A 1C Subsystem B design A 1D Subsystem C design A 1E Program A B 2F Program B C 2G Program C D 2H Subsystem A test E 1I Subsystem B test F 1J Subsystem C test G 1K Integration H, I, J 3L Integration test K 1You are provided with the following information for a project, with activity durations given in weeks: Activity Immediate Optimistic Most Likely Pessimistic Predecessor Time (a) Time (m) Time (b) A ____ 2 3 4 B ____ 2 4 6 C A 1 2 3 D B 3 6 9 E C, D 7 8 9 F D 4 7 10 G E 3 4 5 H E, F…
- You are provided with the following information for a project, with activity durations given in weeks: Activity Immediate Optimistic Most Likely Pessimistic Predecessor Time (a) Time (m) Time (b) A ____ 2 3 4 B ____ 2 4 6 C A 1 2 3 D B 3 6 9 E C, D 7 8 9 F D 4 7 10 G E 3 4 5 H E, F…1. Construct the PERT network for this project 2. Compute for the Earliest Start Time and Latest Start Time, Early Finish and Late Finish and slack time for each activity 3. What is the Critical Path? 4. How long can activity C be delayed without delaying the whole project?A project has these activities, precedence relationships, and activity durations: Activity Immediate Predecessor Activity Activity Duration (Week)a * 3b * 4c * 3d c 12e b 5f a 7g e,f 3 a. Draw a CPM network for the project. b. Provide an overview for the project by computing the duration for each path. c. What is the critical path? What is the project's estimated duration?
- The estimated times and immediate predecessorsfor the activities in a project at George Kyparis’s retinal scan-ning company are given in the following table. Assume thatthe activity times are independent. a) Calculate the expected time and variance for each activity.b) What is the expected completion time of the critical path?What is the expected completion time of the other path inthe network?c) What is the variance of the critical path? What is the vari-ance of the other path in the network?d) If the time to complete path A–C is normally distributed,what is the probability that this path will be finished in22 weeks or less?e) If the time to complete path B–D is normally distributed,what is the probability that this path will be finished in22 weeks or less?f) Explain why the probability that the critical path will befinished in 22 weeks or less is not necessarily the probabil-ity that the project will be finished in 22 weeks or less.According to given project activity table:a. Construct the project network for this project.b. Find the critical activities and critical path of the project.c. Draw the Gannt Chart for the project. T: 7(2) Following is a table listing the project activities, sequencing requirements and other relevant information: Expected Time Direct Cost Activity Preceded By Regular Crash Regular Crash A -- 6 days 2 days $2000 $3800 B -- 12 6 2000 10000 C A 4 2 1000 4000 D B,C 10 6 3400 4600 E D 8 6 2800 3900 F E 6 2 5000 7600 G B, C 18 8 16000 19600 H F, G 6 4 2000 4000 Construct a network including the early and late start and finish times. Identify the normal critical path (s) and the normal expected completion time. Can the project be crushed to last 18 days? Which activities should be crushed and what additional cost?
- Using the information in Table-1, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible: Task Description Duration (WorkingDays) Predecessor/s A Requirement Analysis 5 B Systems Design 15 A C Programming 25 B D telecoms 15 B E Hardware Installation 30 B F Integration 10 C, D G System Testing 10 E, F H Training/Support 5 G I Handover and Go-Live 5 H (i) Determine the critical path of the project (ii) Calculate the planned duration of the project in weeks (iii) Identify any non-critical tasks and the float (free slack) on each.Please assist in detailed explanation on the following question in Project Scheduling: 1) - A company decides to plan a project, with activities, precedence and deterministic durations given in the following table: Activity i Duration (days) Immediate Predecessors A 32 none B 21 none C 30 none D 45 A E 26 A, B F 28 C G 20 E, F Questions: 1.1) What method should be used? Using only one pseudo-activity, draw the project network, with arcs labeled by the activity name and duration. 1.2) Compute and display in a table the earliest and latest starting and finishing times, as well as slack, for each activity, and identify the critical path(s). 1.3) Draw a Gantt chart of the schedule, based on earliest starting times 1.4) Which activities must be completed by day 60 to ensure that the project is not delayed?Consider the following project schedule and respond to the requirements that follow (all times are in days). Activity Predecessors a m b A ---- 12 16 20 B ---- 18 28 32 C A 6 9 12 D B 7 16 19 E C, D 4 10 16 F D, E 18 30 36 G F 5 8 17 H F, G 15 25 35 I F, G 22 26 36 J G 15 19 29 K I, H 24 32 34 (a) Construct a project network diagram using the AON technique, i.e. Activity on Node technique (and NOT AOA or activity on arc technique). Be sure to have a start node and a finish node and include the expected activity times for each node. (b) Determine the critical path and expected project completion time using the “critical path method”. Show ES, EF, LS and LF times, as well as slack for all activities. (c) Determine the standard deviation of the project completion time T; what is the probability that the project will take more…