7- In single surface treatment, the bitumen is a) Sprayed after the fine aggregates are spread and compacted. b) Premixed with fine aggregates and then spread and compacted. c) Sprayed before the fine aggregates are spread and compacted. d) None of the above. 8- To mix asphalt binder with aggregate, it must be made into liquid by a) Heat it c) Suspended it in water with emulsifying agent b) Adding petroleum solvent d) All of the above

Traffic and Highway Engineering
5th Edition
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Garber, Nicholas J.
Chapter18: Bituminous Materials
Section: Chapter Questions
Problem 12P
icon
Related questions
Question
7- In single surface treatment, the bitumen is
a) Sprayed after the fine aggregates are spread and compacted.
b) Premixed with fine aggregates and then spread and compacted.
c) Sprayed before the fine aggregates are spread and compacted.
d) None of the above.
8- To mix asphalt binder with aggregate, it must be made into liquid by
a) Heat it
b) Adding petroleum solvent
d) All of the above
c) Suspended it in water with emulsifying agent
9- The cutback asphalt binder can be classified into fast, medium and slow based on
and------------.
a) Rate of curing and viscosity.
b) Viscosity and penetration.
d) All of the above.
c) Penetration and rate of curing.
10 The compaction device that is used specifically in the Marshall Mix design is
a) Vibro hammer
b) Gyratory compactor
c) Drop hammer
d) California kneading compactor
11- The temperature range which is used for the mixing process of asphalt with aggregate
in the Marshall Mix design is
a) 175 - 190°C
b) 121-145°C
c) 154-160°C d) 138-149°C
12-
The surface of asphalt layer should be
a) Smooth b) Rough c) Sufficient enough to resist friction
d) Very smooth
Transcribed Image Text:7- In single surface treatment, the bitumen is a) Sprayed after the fine aggregates are spread and compacted. b) Premixed with fine aggregates and then spread and compacted. c) Sprayed before the fine aggregates are spread and compacted. d) None of the above. 8- To mix asphalt binder with aggregate, it must be made into liquid by a) Heat it b) Adding petroleum solvent d) All of the above c) Suspended it in water with emulsifying agent 9- The cutback asphalt binder can be classified into fast, medium and slow based on and------------. a) Rate of curing and viscosity. b) Viscosity and penetration. d) All of the above. c) Penetration and rate of curing. 10 The compaction device that is used specifically in the Marshall Mix design is a) Vibro hammer b) Gyratory compactor c) Drop hammer d) California kneading compactor 11- The temperature range which is used for the mixing process of asphalt with aggregate in the Marshall Mix design is a) 175 - 190°C b) 121-145°C c) 154-160°C d) 138-149°C 12- The surface of asphalt layer should be a) Smooth b) Rough c) Sufficient enough to resist friction d) Very smooth
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Asphalt binders and mixtures
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning