A -3% grade meets a +5% grade at a vertex (El. 146.24m) directly under an overpass bridge having underside elevation of 155.74m. A 5 meters clearance under the bridge and the center of the curve was observed. The bridge is having a width of 12 meters. 1. Determine the horizontal length of curve in meters 2. Determine the clearance at the right side of the bridge in meters 3. Determine the clearance at the left side of the bridge in meters 4. Determine the elevation of the invert on center when its location from PC is 75m. The pipe has an outside diameter of 0.4 meters and a thickness of 50mm. The backfill is 0.30 meters in depth. |

Traffic and Highway Engineering
5th Edition
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Garber, Nicholas J.
Chapter15: Geometric Design Of Highway Facilities
Section: Chapter Questions
Problem 7P
icon
Related questions
icon
Concept explainers
Question
A -3% grade meets a +5% grade at a vertex (El. 146.24m) directly under an overpass
bridge having underside elevation of 155.74m. A 5 meters clearance under the bridge
and the center of the curve was observed. The bridge is having a width of 12 meters.
1. Determine the horizontal length of curve in meters
2. Determine the clearance at the right side of the bridge in meters
3. Determine the clearance at the left side of the bridge in meters
4. Determine the elevation of the invert on center when its location from PC is 75m.
The pipe has an outside diameter of 0.4 meters and a thickness of 50mm. The
backfill is 0.30 meters in depth.
Transcribed Image Text:A -3% grade meets a +5% grade at a vertex (El. 146.24m) directly under an overpass bridge having underside elevation of 155.74m. A 5 meters clearance under the bridge and the center of the curve was observed. The bridge is having a width of 12 meters. 1. Determine the horizontal length of curve in meters 2. Determine the clearance at the right side of the bridge in meters 3. Determine the clearance at the left side of the bridge in meters 4. Determine the elevation of the invert on center when its location from PC is 75m. The pipe has an outside diameter of 0.4 meters and a thickness of 50mm. The backfill is 0.30 meters in depth.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Quantity takeoff
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning