A company is accounting for a long-term construction contract where revenue is recognized over time. The project is built to the customer's specifications, and the customer can make changes as construction is ongoing. It is a 3-year, fixed-fee contract that is presently in its first year. The latest reasonable estimates of total contract costs indicate that the contract will be completed at a profit.  The company will submit progress billings to the customer and has reasonable assurance that collections on these billings will be received in each year of the contract. The contract can be canceled at any time by the customer who will retain control of any work done to date. Discuss the following: a. When should revenue from contracts be accounted for overtime versus at a point in time? b. How would the income recognized in each year of this long-term construction contract be determined using the cost-to-cost basis of determining progress toward satisfaction of the performance obligation? c. What is the effect on income, if any, of the progress billings and the collections on these b

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 10C
icon
Related questions
Question

A company is accounting for a long-term construction contract where revenue is recognized over time. The project is built to the customer's specifications, and the customer can make changes as construction is ongoing. It is a 3-year, fixed-fee contract that is presently in its first year. The latest reasonable estimates of total contract costs indicate that the contract will be completed at a profit.  The company will submit progress billings to the customer and has reasonable assurance that collections on these billings will be received in each year of the contract. The contract can be canceled at any time by the customer who will retain control of any work done to date.

Discuss the following:

a. When should revenue from contracts be accounted for overtime versus at a point in time?

b. How would the income recognized in each year of this long-term construction contract be determined using the cost-to-cost basis of determining progress toward satisfaction of the performance obligation?

c. What is the effect on income, if any, of the progress billings and the collections on these billings?

Expert Solution
steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
Individual Income Taxes
Individual Income Taxes
Accounting
ISBN:
9780357109731
Author:
Hoffman
Publisher:
CENGAGE LEARNING - CONSIGNMENT
SWFT Comprehensive Volume 2019
SWFT Comprehensive Volume 2019
Accounting
ISBN:
9780357233306
Author:
Maloney
Publisher:
Cengage
SWFT Individual Income Taxes
SWFT Individual Income Taxes
Accounting
ISBN:
9780357391365
Author:
YOUNG
Publisher:
Cengage
SWFT Comprehensive Vol 2020
SWFT Comprehensive Vol 2020
Accounting
ISBN:
9780357391723
Author:
Maloney
Publisher:
Cengage