A construction company entered into a fixed-price contract to build a soccer stadium for $15,000,000. Construction costs incurred during the first year were $3,675,000, and estimated costs to complete at the end of the year were $6,825,000. The company recognizes revenue over time according to percentage of completion. Fixed-price contract amount: $15,000,000 Construction costs incurred in first year: $3,675,000 Estimated costs to complete at end of first year: $6,825,000 How much revenue and gross profit or loss will appear in the company’s income statement in the first year of the contract? Percentage of completion at end of first year Revenue Gross profit (loss) Nothing in this area will be graded, but it will be submitted with your assignment.
A construction company entered into a fixed-price contract to build a soccer stadium for $15,000,000. Construction costs incurred during the first year were $3,675,000, and estimated costs to complete at the end of the year were $6,825,000. The company recognizes revenue over time according to percentage of completion. Fixed-price contract amount: $15,000,000 Construction costs incurred in first year: $3,675,000 Estimated costs to complete at end of first year: $6,825,000 How much revenue and gross profit or loss will appear in the company’s income statement in the first year of the contract? Percentage of completion at end of first year Revenue Gross profit (loss) Nothing in this area will be graded, but it will be submitted with your assignment.
Financial Accounting Intro Concepts Meth/Uses
14th Edition
ISBN:9781285595047
Author:Weil
Publisher:Weil
Chapter8: Revenue Recognition, Receivables, And Advances From Customers
Section: Chapter Questions
Problem 48P
Related questions
Question
A construction company entered into a fixed-price contract to build a soccer stadium for $15,000,000. Construction costs incurred during the first year were $3,675,000, and estimated costs to complete at the end of the year were $6,825,000. The company recognizes revenue over time according to percentage of completion. | ||||
Fixed-price contract amount: | $15,000,000 | |||
Construction costs incurred in first year: | $3,675,000 | |||
Estimated costs to complete at end of first year: | $6,825,000 | |||
How much revenue and gross profit or loss will appear in the company’s income statement in the first year of the contract? | ||||
Percentage of completion at end of first year | ||||
Revenue | ||||
Gross profit (loss) | ||||
Nothing in this area will be graded, but it will be submitted with your assignment. |
AI-Generated Solution
AI-generated content may present inaccurate or offensive content that does not represent bartleby’s views.
Unlock instant AI solutions
Tap the button
to generate a solution
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning