Question
A contract required the job to be completed July 15. The engineer ordered the contractor to suspend operations from May 1 to May 15, and then changed the completion date to July 31. Was the change in completion data appropriate?
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Issues during construction
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,