A contract required the job to be completed July 15. The engineer ordered the contractor to suspend operations from May 1 to May 15, and then changed the completion date to July 31. Was the change in completion data appropriate?
A contract required the job to be completed July 15. The engineer ordered the contractor to suspend operations from May 1 to May 15, and then changed the completion date to July 31. Was the change in completion data appropriate?
Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter14: Pricing General Expenses
Section: Chapter Questions
Problem 4RQ
Related questions
Question
A contract required the job to be completed July 15. The engineer ordered the contractor to suspend operations from May 1 to May 15, and then changed the completion date to July 31. Was the change in completion data appropriate?
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,