A contractor is working on a $500,000 construction contract that was scheduled to be completed within 12 months; however, the owner delayed the contractor by 1 month. Using the Eichleay formula, compute the amount of reimbursement that the contractor can claim for home office overhead if the contractor’s total billing for the contract period was $10,000,000 and the total overhead for the contract period was $300,000.

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter18: Life-cycle Costing
Section: Chapter Questions
Problem 16RQ
icon
Related questions
Question

A contractor is working on a $500,000 construction contract that was scheduled to be completed within 12 months; however, the owner delayed the contractor by 1 month. Using the Eichleay formula, compute the amount of reimbursement that the contractor can claim for home office overhead if the contractor’s total billing for the contract period was $10,000,000 and the total overhead for the contract period was $300,000.

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 3 images

Blurred answer
Knowledge Booster
Pricing of General Work
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,