A potential site for a reservoir is being evaluated for two mutually exclusive options: a small water supply reservoir or a large flood control reservoir. Cost and benefit data on the two options are provided below. Interest rate to be used is 10%. Each alternative has an initial cost, an annual operating cost, and an annual benefit. Each alternative also has a mid-life maintenance cost that occurs 20 years after the start of the project.

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
A potential site for a reservoir is being evaluated for two mutually exclusive options: a small water supply
reservoir or a large flood control reservoir. Cost and benefit data on the two options are provided below.
Interest rate to be used is 10%. Each alternative has an initial cost, an annual operating cost, and an annual
benefit. Each alternative also has a mid-life maintenance cost that occurs 20 years after the start of the
project.
Alternative 1 (Water Supply ($
Alternative 2 (Flood Control ($
million))
million))
Initial cost
52
71
Annual operating cost
0.6
0.4
Annual benefit
10
11
Maintenance cost in year
2
20
Lifetime (years)
44
44
Compute PWNB of Alternative 1 and 2
precision guide: [0.000, 0.000]
] •
answer
Compute EUANB of Alternative 1 and 2
precision guide: [0.000, 0.000]
answer
What is the best option using PWNB and EUANB
precision guide: [integer, integer]
]] •
answer
Transcribed Image Text:A potential site for a reservoir is being evaluated for two mutually exclusive options: a small water supply reservoir or a large flood control reservoir. Cost and benefit data on the two options are provided below. Interest rate to be used is 10%. Each alternative has an initial cost, an annual operating cost, and an annual benefit. Each alternative also has a mid-life maintenance cost that occurs 20 years after the start of the project. Alternative 1 (Water Supply ($ Alternative 2 (Flood Control ($ million)) million)) Initial cost 52 71 Annual operating cost 0.6 0.4 Annual benefit 10 11 Maintenance cost in year 2 20 Lifetime (years) 44 44 Compute PWNB of Alternative 1 and 2 precision guide: [0.000, 0.000] ] • answer Compute EUANB of Alternative 1 and 2 precision guide: [0.000, 0.000] answer What is the best option using PWNB and EUANB precision guide: [integer, integer] ]] • answer
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 4 images

Blurred answer
Knowledge Booster
Water withdrawal
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning