A project has estimated optimistic (a), most likely (m) and pessimistic (b) times for activity D
as 7, 8 and 14 days, respectively. What is the mean AND variance for activity D, respectively
(to 1 decimal place):
Select one:
a. 8.8 and 1.2
b. 8.5 and 0.7
O c. 8.8 and 0.7
d. 9.7 and 1.4
Transcribed Image Text:A project has estimated optimistic (a), most likely (m) and pessimistic (b) times for activity D as 7, 8 and 14 days, respectively. What is the mean AND variance for activity D, respectively (to 1 decimal place): Select one: a. 8.8 and 1.2 b. 8.5 and 0.7 O c. 8.8 and 0.7 d. 9.7 and 1.4
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Recommended textbooks for you
Glencoe Algebra 1, Student Edition, 9780079039897…
Glencoe Algebra 1, Student Edition, 9780079039897…
Algebra
ISBN:
9780079039897
Author:
Carter
Publisher:
McGraw Hill