a) The expected​ (estimated) time for activity C is 13.33 weeks. ​(Round your response to two decimal​ places.)   ​b) The variance for activity C is 1.78 weeks. ​(Round your response to two decimal​ places.)   ​c) Based on the calculation of the estimated​ times, the critical path is A - C - F - H - J - K   . ​d) The estimated time for the critical path is [ ? ] enter your response here weeks. ​(Round your response to two decimal​ places.)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%
Ross​ Hopkins, president of Hopkins​ Hospitality, has developed the​ tasks, durations, and predecessor relationships in the following table for building new motels. 
Activity    a    m    b    Immediate Predecessor(s)    Activity    a    m    b    Immediate Predecessor(s)
A    6    8    12    -    G    2    3    4    C, E
B    1    9    24    A    H    2    2    2    F
C    8    14    16    A    I    7    7    7    F
D    4    7    10    A    J    6    7    12    D, G, H
E    1    2    4    B    K    1    1    4    I, J
F    6    9    20    C, E                    
a) The expected​ (estimated) time for activity C is 13.33
weeks. ​(Round your response to two decimal​ places.)
 
​b) The variance for activity C is 1.78
weeks. ​(Round your response to two decimal​ places.)
 
​c) Based on the calculation of the estimated​ times, the critical path is
A - C - F - H - J - K
 
.
​d) The estimated time for the critical path is [ ? ]
enter your response here
weeks. ​(Round your response to two decimal​ places.)
Expert Solution
Step 1 Introduction:-

A network diagram shows the sequence of the task that is done to complete a project. It usually shows the link of each task with the duration taken by each activity with respect to the completion of the project. Each task is shown with the nodes that are connected with each other with the help of arrows. There are 2 types of network diagrams:- CPM and PERT.

trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Follow-up Questions
Read through expert solutions to related follow-up questions below.
Follow-up Question

e) The activity variance along the critical path is [ ? ]

weeks. ​(Round your response to two decimal​ places.)

Solution
Bartleby Expert
SEE SOLUTION
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.