(a) Using the given IDF curves and the Rational method, calculate the 50-years design peak flow (in cfs) at the catchment outlet.
Q: Given a rectangular channel cross-section with a bottom width of 6m with the bottom slope is 1:1010…
A:
Q: Situation 1: Give the discharge/flow rate in (m/s) of the system with a constant velocity of 2.5m's…
A:
Q: The depth of flow at the upstream of a weir is 2 m and at the downstream it gets 0.5 m. Calculate…
A: Given: Depth at upstream side, y1 = 2 m Depth at downstream side, y2 = 0.5 m
Q: Determine the flow over a suppressed weir 3.00 m long and 1.20 m high under a head 0.914 m. The…
A:
Q: A semi-circular flume 1.2m in diameter is used to carry a flow of 1.75m^3/s when flowing full. If…
A: Diameter of semi-circular flume(D)=1.2 m, Flow rate (Q)= 1.75 m3/sec, Manning's constant(n)=0.012.
Q: An rectangular orifice with height 0.4 m and width of 0.6 m was used to measure the flow of a…
A:
Q: Two reservoirs are connected by 198ft of 2-in diameter tubing. What is the flow rate when the…
A: Answer We know that Flow rate in tube is given by Q = A*V A = cross section area of tube V =…
Q: 1. A rectangular open channel of width 5.0 m is carrying a discharge of 100 m3 /s. The Froude number…
A:
Q: 4. (a) Determine the critical depth of flow, ye, and specific energy, Ee, at the critical flow…
A: Given data : Width (B)=4.5 mDischarge (Q)=2.5 m3/s
Q: Uniform flows occur in a 10 meter wide rectangle channel. The flow in the channel is 18.4 m³/s and…
A: Minimum Specific Energy of flow is given by ; Emin Emin = 1.5 * yc Where ; yc = (q2g)13
Q: Reservoir, 8,450 ft
A:
Q: With a total flow of 14 cfs, determine the division of flow and the head loss from A to B. L = 6000…
A: ASKED: To determine the flow through each pipe and the head loss. Given, Flow rate of the system…
Q: The elevations of the three-reservoir system are shown in the figure. Considering the pipe data…
A: Given:- The elevation of reservoir A = 150 m The elevation of reservoir B = 120 m The elevation of…
Q: Q4: If the height of the flood hydrograph resulting from a 6-hour rainstorm is over a certain…
A:
Q: (b) Consider a rectangular channel section carrying a discharge 'd per unit width'V. (1) Prove that…
A:
Q: Three reservoirs are connected in a common junction. Following are the pertinent information:…
A: Given data Reservoir A: Elevation 90 m, 1800 m pipe with 400 mm diameter and f = 0.02 Reservoir B:…
Q: The flow rates measured during a precipitation at the outlet of a basin with an area of 10800…
A: Surface runoff= Total flow-base flow Time(minute) Discharge (Q) Base flow surface runoff 1cm…
Q: Calculate the flow discharge in a 7-m-wide rectangular horizontal channel where the flow depth and…
A: Given, width of channel, W = 7m Depth, d = 0.7m Velocity, v= 7m/s To calculate: Discharge (Q)
Q: A steady discharge of 60 m³/s passing through a trapezoidal irrigation channel with a bottom width…
A: Given data, Discharge, Q = 60 m3/s Bottom width = 5m Bed slope = 0.01% n = 0.025 Trapezoidal…
Q: A discharge of 600 liters/sec flows through a pipe having a diameter of 400 mm., length of 40 m.…
A:
Q: Example. 9.2. A rectangular notch has a discharge of 0-24 m'/s, when head of water is 800 mm. Find…
A:
Q: Determine the downstream depth in a horizontal rectangular channel in which th bottom rises 0.75 ft,…
A: The given data is: Discharge, Q=550 cfs Width, B=5 ft q=Q/B q=550/5=110 ft2/s
Q: Q3/ determine the discharge in the compound open channel shown in figure assume a bed slope (O.001)…
A: Bed slope (s) = 0.001 Mannings coefficient (n) = 0.03 Area of channel (A) = ( 5 x 0.5 ) + ( 0.2 x…
Q: Calculate the discharge (m³/s) in a river that is affect by back-water, corresponding to fall (F₂)…
A: given- fall value-F2=1.4 mfall value-F1=0.6 mdischarge for fall value of F1Q1=280 m3/sm=0.5
Q: Reservoirs A and D are connected by a pipeline system as shown below. The water surface elevations…
A: Given, Surface elevation of reservoir A = 100 ft Surface elevation of reservoir B = 80 ft
Q: Calculate discharge for a rectangular Sarda fall having Crest length 10 m Top width 3m and Depth of…
A: Sarda fall Sarda-type falls are made up of modest falls that result in slow energy dissipation of…
Q: Question 4: A rectangular channel conveys Q=(10+b) m³/s discharges and has a K=(50+a). a) Calculate…
A: Given, Discharge (Q) = 14 m3/s K = 57
Q: A rectangular channel of width 500 mm and a uniform flow depth of 250 mm has a discharge of 0.1…
A: Given that....
Q: #Q 3.5.3 A Flow net is plotted for a homogeneous earthern dam of 30.0 m height with a free board of…
A: Given data,
Q: The critical depth of flow (in m) for the parabolic channel as shown in the figure for a discharge…
A:
Q: An S-curve hydrograph has been obtained for catchments of 270 km2 from a 3 hour unit hydrograph. The…
A:
Q: 2) The hydrograph given below is to be routed in a rectangular reservoir with an initial water…
A: This problem will be done by using Modified Pul's method.
Q: A rectangular channel carries a discharge of 20 m3/sec with a width of 1 meter and a manning…
A: Using mannings…
Q: A rectangular channel of width 550 mm has a discharge of 0.1 m/s and a uniform flow depth of 250 mm.…
A: Given: Width of channel, W = 550 mm Discharge, Q = 0.1 m3/s Depth of flow, H = 250 mm C = 55
Q: Situation 1: Give the discharge/flow rate in (m³/s) of the system with a constant velocity of 2.5…
A: Given data : The magnitude of velocity of flow is V=2.5 m/s The magnitude of diameter of pipe is…
Q: The flow rates measured during a precipitation at the outlet of a basin with an area of 32400…
A: surface runoff=Total flow-base flow Time (t) Total flow (Q) Base flow Surface runoff 1 cm…
Q: The top width and the depth of flow in a triangular channel were measured as 5 m and 1 m…
A:
Q: Determine the flow over a suppressed weir 3.00 m long and 1.20 m high under a head 0.914 m. The…
A: Length and Width of flow over suppressed weir 3 meter long have been given and it has been asked to…
Q: The catchment area of New Delhi is 81 km2, then m3/s. the maximum flood flow will be (Use the value…
A:
Q: a) Using differential equation of gradually varied flow, show that dy/dx is positive for Sı, M1 and…
A:
Q: Compute the discharge capacity of 3-m concrete (rough) pipe carrying water at 10°C. It is allowed…
A: Concrete is a basic combination of cement, air, water, sand, and gravel. A normal concrete mix…
Q: A 6-hour unit hydrograph (UH) of a catchment is triangular in shape with a total time base of 36…
A: Please refer the attached image for complete solution. THANK YOU !
Q: With a flow of 86.4 cu. m. per sec., determine the approximate diameter size of a pipe in mm…
A:
Q: The Froude number of a flow in a triangular channel (vertex angle 90°) is 0.8. If the depth of flow…
A:
Q: Find the depth, specific energy and slope for critical flow condition for given discharge of 25…
A: Given that: Discharge in the channel, Q = 25 m3/s Width of the channel, B = 10 m…
Q: 2) A rectangular weir of length 100 m has a head of water of 1.5 m over it and the value of velocity…
A: Given: Length of weir, L = 100 m Head of water, H = 1.5 m Velocity of approach, Va = 0.5 m/s…
Q: A 30 cm diameter pipe divides into a 20 cm diameter branch and a 15 cm diameter branch. The total…
A: Given data : The value of Total discharge (Q)=0.3 m3/sDiameter of pipe 1 (D1)=20 cmDiameter of pipe…
Q: Hydraulic jump forms in a rectangular channel carrying a unit discharge of 1.019 m3/sec/m at a depth…
A: Given data in question Discharge per unit width Depth of flow before jump To find out Frauds…
Q: Q: The table below represents the elevation-area curve for a res 32 000 000 m², the elevation of…
A: By trapezoidal formula h=intreval of elevation =2 elevation (m) Area (km/square) Equation…
Q: 116 ft3/s-day. The reservoir routing curves graph is given in Figure 1. Perform calculation until…
A: Given, Spillway crest elevation, H= 50 ft Coefficient, C=3 Spillway length, L=35 ft
Step by step
Solved in 2 steps with 2 images
- Consider a watershed with a drainage area of 10 square miles and a mainstream length of 7.5 miles. The main channel extends from the watershed outlet to the point opposite the centre of gravity of the watershed over a distance of 3.5 miles. Given a time of concentration (Ct) of 1.5 hours and a dimensionless slope of the watershed (Cp) of 0.5, determine the standard synthetic unit hydrograph for this basin. What is the duration? Using Snyder’s method, calculate the 45-minute unit hydrograph parameter10-min unit hydrograph for a catchment is given in Table 1 below. Table 1: 10-min Unit Hydrograph Time (min) 05 10 15 20 25 30 35 40 45 50 1.75 1.95 2.0 1.8 1.25 0.6 Flow (m³/s) 0 0.5 1.0 1.4 0 a. What is the area of the catchment? b. Construct a storm hydrograph resulting from the 40-min rainfall event. The rainfall excess depths are provided in Table 2. Determine the peak discharge resulting from this 40-min rainfall event. Table 2: Rainfall Excess Depths Rainfall Excess (mm) Time (min) 0-20 4 20-40 6Question 2 Route the inflow hydrograph through a reservoir as indicated in Table 2. The crest height of the spillway is 50 ft and storage capacity at this level is 116 ft3/s-day. The reservoir routing curves graph is given in Figure 1. Perform calculation until the outflow value is equal to zero. Based on the obtained result, plot the inflow and outflow hydrographs. Table 2 0.4 1.6 2 2.4 2.8 Time (day) 0 Flow (ft³/s) 0 0.8 120 1.2 229 56 380 268 155 50 Figure 1 25/atO (ft/s.day)-primary x-axis 700 800 900 1000 54.0 53.5 53.0 52.5 52.0 51.5 Elevation vs Storage (curve a) Elevation vs 25/De-O (curve b) Elevation vs Outflow (curve c) 51.0 50.5 50.08 49.5 110 230 0 Water Surface Elevation (tt) 400 W 500 130 100 600 150 200 190 170 210 Storage (ft³/s.day) - secondary x-axis 300 400 500 Outflow (ft³/s.day) - tertiary x-axis 600 250 1100 700
- Annual flood data of the river Kaveri covering the period from 1952 to 1983 yielded a discharge of 29,600 m/sec and a standard deviation of 14,860 m/sec. For a proposed bridge on this river near this site, it is decided to have an acceptable risk of 10% in its expected life of 50 years. What will be the design flood discharge (m3/sec) using Gumbel's method? [Take n = 50 years, Yn = 0.538, Sn = 1.1193]A catchment area is presented in the Figure 1. Six rainfall gauges A, B, C, D, E and F are spread over this watershed and nearby. The inter isohyets areas I, II, II, IV and V are given as 20, 50, 70, 90, and 10 km? respectively. All the rainfall and isohyets are given in cm. Estimate the mean precipitation over this catchment area using arithmetic mean and isohyetal methods.Q2) Annual rainfall and runoff values of a catchment for a period of 10 years are given below. Analyze the data to (a) develop a non-linear correlation equation to estimate annual runoff volume for a given annual rainfall value, (b) Estimate r values for the equation, (c) Estimate the runoff depth when the rainfall depth is (i) 350 mm (ii) 600 mm. 2010 2011 2017 2018 2019 Year Annual 2012 2013 2014 2015 2016 Rainfall 361 408 217 324 510 488 275 392 296 420 (mm) Annual Runoff (mm) 145 160 90 130 205 195 110 157 120 165
- Hydrology 1. List the factors affecting the seasonal and annual runoff (Yield) of a catchment. Describe briefly the interactions of factors listed by you. 2. With the help of typical hydrographs describe the salient features of (i) Perennial,(ii) intermittent, and (iii) ephemeral steams. 3. Explain briefly:(a) Water year(b) Natural (Virgin) flow.A wastewater treatment plant discharges of effluent into a stream. Just upstream from the discharge point, the stream has an ultimate BOD of 5 mg/L.Assuming a cross-sectional area for the stream equal to 100 m2, what ultimate BOD (in mg/L) would you expect to find at a point of 15,000 m downstream? Wastewater Flow: 1 m3/secBOD (ultimate): 40 mg/LRiver Flow: 10 m3/secDeoxygeneation constant kd: 0.22 day-1The 1-hour unit (25mm) hydrograph for an ungauged watershed is estimated by a watershed modeler to be as follows: a linear increase in discharge to be 4 m³/s at 1 hour; and then, b) a further increase a) to 10 m³/s at 2 hours; and then, c) a linear decrease to 4 m³/s at 3 hours; and then d) followed by a linear decrease to zero at 4 hours. Determine the values of. 1). two hour unit hydrograph 2). four hour unit hydrograph.
- From the basin map of a given watershed, the following quantities are measured: L = 150km, L. = 75km, and drainage area = 3500 km2. From the unit hydrograph derived for the watershed, the following are determined: tR = 12h, tpR = 34h, and peak discharge = 157.5 m/s-cm. Determine the coefficients C; and C, for the synthetic unit hydrograph of the watershed. Compute the six – hour synthetic unit hydrograph of a watershed having a drainage area of 25O0km2 with L = 100km and L. = 50km. This watershed is a sub – drainage area of the watershed in the first problem.Example 8. Develop a 30-minute SCS triangular unit hydrograph for a watershed of area 550 ha and time of concentration of 50 minutes.A 1 : 100 scale model of river is to be tested in a laboratory. The highest flood in river is 1000 m^3 /s. The corresponding discharge to be maintained in the model is ______ m^3 /s. (round off to 2 decimal places)