A waste-holding lagoon situated near the main plant of a chemical company receives sludge on a daily basis. When the lagoon is full, it is necessary to remove the sludge to a site located 4.95 kilometers from the main plant. Currently, when the lagoon is full, the sludge is removed by pumping it into a tank truck and hauling it away. This process requires the use of a portable pump that has an initial cost of $800 and an 8-year life. The company can operate the pump at a cost of $25 per day, but the truck and driver cost $110 per day. Alternatively, the company has a proposal to install a pump and pipeline to the remote site. The pump would have an initial cost of $600, a life of 10 years, and a cost of $3 per day to operate. (a) If the MARR is 15% per year and the pipeline will cost $3.52 per meter to construct, how many days per year must the lagoon require pumping to justify construction of the pipeline? (b) The lagoon was pumped 40 times last year. Which alternative would have been cheaper? How do you know this is the correct answer?

Solid Waste Engineering
3rd Edition
ISBN:9781305635203
Author:Worrell, William A.
Publisher:Worrell, William A.
Chapter2: Municipal Solid Waste Characteristics And Quantities
Section: Chapter Questions
Problem 2.17P
icon
Related questions
Question

A waste-holding lagoon situated near the main plant of a chemical
company receives sludge on a daily basis. When the lagoon is full, it is necessary to
remove the sludge to a site located 4.95 kilometers from the main plant. Currently,
when the lagoon is full, the sludge is removed by pumping it into a tank truck and
hauling it away. This process requires the use of a portable pump that has an initial
cost of $800 and an 8-year life. The company can operate the pump at a cost of $25
per day, but the truck and driver cost $110 per day.
Alternatively, the company has a proposal to install a pump and pipeline to the
remote site. The pump would have an initial cost of $600, a life of 10 years, and a
cost of $3 per day to operate. (a) If the MARR is 15% per year and the pipeline will
cost $3.52 per meter to construct, how many days per year must the lagoon require
pumping to justify construction of the pipeline? (b) The lagoon was pumped
40 times last year. Which alternative would have been cheaper? How do you know
this is the correct answer? 

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Mechanical processes
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Solid Waste Engineering
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,