4.10 A well is being drilled at a vertical depth of 12,200 ft while circulating a 12-lbm/gal mud at a rate of 9 bbl/min when the well begins to flow. Fifteen bar- rels of mud are gained in the pit over a 5-minute period before the pump is stopped and the blowout preventers are closed. After the pressures stabil- ized, an initial drillpipe pressure of 400 psia and an initial casing pressure of 550 psia were recorded. The annular capacity opposite the 5-in., 19.5-lbf/ft drillpipe is 0.0775 bbl/ft. The annular capacity op- posite the 600 ft of 3-in. ID drill collars is 0.035 bbl/ft. Assume M-16 and T-600°R. d. Compute the pressure that will be observed at the casing depth of 4,000 ft when the top of the kick zone reaches the casing if the kick is circulated from the well before increasing the mud density. Answer: 3,198 psia. e. Compute the annular pressure that will be observed at the surface when the top of the kick zone reaches the surface if the kick is circulated to the surface before increasing the mud density. The annular capacity inside the casing is also 0.0775 bbl/ft. Answer: 1,204 psia. f. Compute the surface annular pressure that would be observed at the surface when the top of the kick zone reaches the surface if the mud density is increased to the kill mud density before circula- tion of the well. Answer: 1,029 psia.

Oh no! Our experts couldn't answer your question.

Don't worry! We won't leave you hanging. Plus, we're giving you back one question for the inconvenience.

Submit your question and receive a step-by-step explanation from our experts in as fast as 30 minutes.
You have no more questions left.
Message from our expert:
Our experts are unable to provide you with a solution at this time. Try rewording your question, and make sure to submit one question at a time. A question credit has been added to your account for future use.
Your Question:
4.10 A well is being drilled at a vertical depth of 12,200
ft while circulating a 12-lbm/gal mud at a rate of 9
bbl/min when the well begins to flow. Fifteen bar-
rels of mud are gained in the pit over a 5-minute
period before the pump is stopped and the blowout
preventers are closed. After the pressures stabil-
ized, an initial drillpipe pressure of 400 psia and an
initial casing pressure of 550 psia were recorded.
The annular capacity opposite the 5-in., 19.5-lbf/ft
drillpipe is 0.0775 bbl/ft. The annular capacity op-
posite the 600 ft of 3-in. ID drill collars is 0.035
bbl/ft. Assume M-16 and T-600°R.
d. Compute the pressure that will be observed at
the casing depth of 4,000 ft when the top of the
kick zone reaches the casing if the kick is circulated
from the well before increasing the mud density.
Answer: 3,198 psia.
e. Compute the annular pressure that will be
observed at the surface when the top of the kick
zone reaches the surface if the kick is circulated to
the surface before increasing the mud density. The
annular capacity inside the casing is also 0.0775
bbl/ft. Answer: 1,204 psia.
f. Compute the surface annular pressure that
would be observed at the surface when the top of
the kick zone reaches the surface if the mud density
is increased to the kill mud density before circula-
tion of the well. Answer: 1,029 psia.
Transcribed Image Text:4.10 A well is being drilled at a vertical depth of 12,200 ft while circulating a 12-lbm/gal mud at a rate of 9 bbl/min when the well begins to flow. Fifteen bar- rels of mud are gained in the pit over a 5-minute period before the pump is stopped and the blowout preventers are closed. After the pressures stabil- ized, an initial drillpipe pressure of 400 psia and an initial casing pressure of 550 psia were recorded. The annular capacity opposite the 5-in., 19.5-lbf/ft drillpipe is 0.0775 bbl/ft. The annular capacity op- posite the 600 ft of 3-in. ID drill collars is 0.035 bbl/ft. Assume M-16 and T-600°R. d. Compute the pressure that will be observed at the casing depth of 4,000 ft when the top of the kick zone reaches the casing if the kick is circulated from the well before increasing the mud density. Answer: 3,198 psia. e. Compute the annular pressure that will be observed at the surface when the top of the kick zone reaches the surface if the kick is circulated to the surface before increasing the mud density. The annular capacity inside the casing is also 0.0775 bbl/ft. Answer: 1,204 psia. f. Compute the surface annular pressure that would be observed at the surface when the top of the kick zone reaches the surface if the mud density is increased to the kill mud density before circula- tion of the well. Answer: 1,029 psia.
Knowledge Booster
Storm sewers and detention
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals of Geotechnical Engineering (MindTap…
Fundamentals of Geotechnical Engineering (MindTap…
Civil Engineering
ISBN:
9781305635180
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning