a. Which activity has the largest slack?
Q: First Printing and Copy Center has 4 jobs to be scheduled. Production scheduling personnel are…
A: Updated chart from above-
Q: Define the term Slack-Time?
A: Project management can be termed as the application of knowledge, techniques, tools, skills, and…
Q: What is the idle time at the paint work center for the optimal schedule?
A: The smallest time is located in Job E (1 hour). Since the time is in First Work Center (Body),…
Q: - Find slack time using cpm approach?
A: Given that: Activities a m b A 3 6 8 B 2 4 4 C 1 2 3 D 6 7 8 E 2 4 6 F 6 10 14 G 3…
Q: Duration of Dummy activity is always constant IS Select one: O True O False
A: Dummy activity does not consume time and resource. Duration of dummy activity is not always…
Q: 77 During the execution of a project, it is discovered that not all work packages included the…
A: Project Execution is the stage of the project life cycle in which the work is completed and the…
Q: 2- Find the completion time (TE).
A: TE stands for the expected duration. It means the expected time duration that each activity will…
Q: How, precisely, does project scheduling differ from the scheduling of ongoing operations?
A: The project schedule contains project-related activities and deliverables, usually with a start and…
Q: How Horizon Consulting established its project lifecycle?
A: So we can say that where improved results happen at whatever point tries are made to give included…
Q: A, B, and C, activities are the immediate predecessors for Y activity. If the earliest finish times…
A: THE ANSWER IS AS BELOW:
Q: Explain : Activity time, Gantt chart, Critical path, Slack time, Crashing.
A: PART A: - Activity period may be a noun that represents the particular amount of your time that…
Q: The method used in scheduling a project is: (A) A schedule of break-down of orders (B) Outline…
A: Here, question has asked the method that is used in scheduling a project, there are several methods…
Q: Describe the meaning of slack, and discuss how it can be determined.
A: Project management is the application of processes, methods, skills, knowledge and experience in…
Q: An activity originally estimated to cost $100,000 and require 30 weeks to complete. Now the activity…
A: Earned value is the measurement of completed work from the total plan of the project.
Q: (b) Oman Steel Company is currently having five jobs to be completed in details of which is given in…
A: Ans 1: Given data Remaining processing time (Days ) Jobs (in the order they arrive )…
Q: Can activities in a work breakdown structure wbs be planned concurrently? Why or why not
A: WBS is a tool that provides guidance for schedule development and control by providing detailed…
Q: SESSION 2: Tutorial Homework Activity Duration Additional Information (days) The project starts with…
A: 1. Activity Immediate Predecessors Duration A - 5 B A 3 C - 1 D…
Q: d. How much slack is in Activity C? What does this mean? e. How much slack is in Activity E?
A: The critical task is the task that performs the operations on the critical path of the project that…
Q: Ahead of schedule Behind schedule a. The status of the project in terms of schedule: Under budget…
A: Here, To understand whether the project is ahead of schedule or behind the schedule, we would…
Q: Draw the A-O-A network of a project having seven activities. Activity A, B, and C that run…
A: Activity A,B,C run concurrently which means we can run them parallely
Q: How does the Work Breakdown Structure differ from the project network?
A: Work Breakdown structure is the clear breakdown of the entire working processes of the project into…
Q: The time by which an activity can be rescheduled without affecting the otheractivities - preceding…
A: (B) Independent float.
Q: Activity Q on a project has exactly 4 successors E, F, G, and H whose late start days are 20, 12,…
A: Below is the solution:-
Q: e of it to p
A: The schedule, resources required, and the actuality of the project's delivery are all determined by…
Q: Create a schedule for this house to be completed within the time frame Jan 4 to April 4. The…
A: a. the solution to the question has been marked in an excel sheet and attached herewith. Please find…
Q: . How does resource scheduling reduce flexibility in managing projects?
A: Resource scheduling refer to the set of actions or the processes deployed by the organizations to…
Q: What is the Latest Finish Time Rule?
A: The critical path method is an algorithmic method used to schedule project activities in a manner so…
Q: Distinguish the advantages and disadvantages of a network over a Gantt chart for project scheduling.
A: The elementary difference between the Gantt chart & the network diagram described as follows:…
Q: What are the values of the slack for activities B and F?
A:
Q: How many activities have non-zero free slack? Choose. How many activities have non-zero total slack,…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: The critical path technique is important in project scheduling, but what exactly does it do?
A: Each project features a few activities that are necessary for timely fulfillment. These are named…
Q: You are one of three carpenters assigned to complete a short construction project. Right before the…
A: Fro the given data: note : Early start - ES Early finish - EF Late start- LS Late finish -LF The…
Q: The difference between the late and early start time for an activity is?
A: Answer given below:
Q: How do we calculate slack?
A:
Q: NSTRUCTIONS: Draw the AON network for Exercise 14 (pg ASSIGNMENT 200 & 201). Complete the forward…
A: Project management is the process of overseeing a team's activity to complete all project objectives…
Q: What role does a work breakdown structure have in preventing scope creep?
A: Project management is the management in which different types of skills and knowledge are required…
Q: If an activity has a zero slack, it: A. Is on the critical path. B. Must be a noncritical activity.…
A: Question: If an activity has a zero slack, it: A. Is on the critical path.B. Must be a noncritical…
Q: Identify the term being described for each of the following: g. Shortening an activity by allocating…
A: The term used to determine shortening of an activity by allocating additional resources is called…
Q: No. Activity Duration Successor Relationship Lag (week) (week) В, С, D A-B (S-S) A-C (F-S) A-D (F-S)…
A: The question is related to Crtical Path. The Path having the longest duration is the Criticial Path.…
Q: Define schedule activity lag
A: The process of schedule development includes: - 1.Identification of all activities, 2. Sequencing…
Q: An activity originally estimated to cost $100,000 and require 30 weeks to complete. Now the activity…
A: ANSWER IS AS BELOW:
Q: 3. Compute the early, late, and slack times for the activities in the network that follows, assuming…
A: The activity value in the network is as follows:
Q: What does it mean for a path to have three weeks of slack? Does each activity necessarily have three…
A: Slack on the project path is important to the managers. It is the amount of time when the activities…
Q: Slack time for each of the activities is? (Activity A-G)
A: Find the given details below: Given Details: Activity Immediate Predecessor(s) Time (days) A…
Step by step
Solved in 3 steps with 2 images
- As the pandemic waned, an educational institution was faced with the imperative of refurbishingand retrofitting its premises to facilitate reopening for blended modality in learning. Essential tasksincluded expanding certain spaces, fitting canteen tables with partitions and acquiring andinstalling equipment. A project manager was engaged to ensure readiness in three weeks.Information compiled on the project scope, such as activity times and relationships, is presentedbelow: Activity Immediate Predecessor Time (Days) A - 2 B A 5 C A 2 D A 6 E B 6 F C, D 3 G D…The following represents a project with known activity times. All times are in weeks.Activity ImmediatePredecessor TimeA - 4B - 3C - 1D B 2E A 3F C, E 5G D 3H F 2I G, H 3J I 6K I 4L J 21) Create a CPM Network. 2) What is the total project time? 3) What activities are on the critical path?4) Compute the slack time for all non-critical activities. 5) What is the latest possible start time for activity D? Please show all work in excel and how you did it, Thank you!Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 7 − E 4 B B 6 − F 5 B C 4 A G 10 C, E D 2 A H 8 D , F Part 2 Dave's earliest start (ES) and earliest finish (EF) are: Part 3 Part 4 Part 5 Part 6 Part 7 Part 8 Part 9 Part 10 Dave's latest start (LS) and latest finish (LF) are:…
- Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 7 − E 5 B B 8 − F 6 B C 4 A G 11 C, E D 3 A H 7 D , F Part 2 Dave's earliest start (ES) and earliest finish (EF) are: Part 3 Part 4 Part 5 Part 6 Part 7 Part 8 Part 9 Part 10 Dave's latest start (LS) and latest finish (LF) are:…A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 50 days? Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost A -- 8 $12,000 5 $21,000 B A 12 $20,000 9 $30,000 C A 15 $24,000 10 $60,000 D B 3 $10,000 2 $15,000 E C 9 $17,000 6 $34,000 F E 7 $5,000 6 $6,000 G D 8 $14,000 6 $20,000 H A 12 $22,000 10 $30,000 I H 6 $50,000 5 $55,000 J F, G, I 11 $33,000 9 $50,000Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)A 7 - E 4 BB 8 - F 7 BC 4 A G 11 C, ED 1 A H 6 D , F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES EF A 0 7 B 0 8 C 7 11 D 7 88 E 8 12 Part 7 F ? ? G ? ? H ? ?
- Please, I need help because I have no idea how to do any of these. 11. Building a backyard swimming pool consists of nine major activities. The activities and their immediate predecessors are shown. Develop the project network. For question number 12, you need to refer to question number 11. Also the first picture is for #11 and second picture(image) is for #12 12. Assume that the activity time estimates (in days) for the swimming pool construction project in Problem 11 are as follows: a. What are the critical activities? b. What is the expected time to complete the project? c. Based only on the critical path, what is the estimated probability that the project can be completed in 25 or fewer days?To design a new app, a project manager has gathered the time information foreach activity as shown in the following table:Activity Predecessors Optimistic Most Likely PessimisticA / 1 4 7B / 2 6 10C B 3 3 9D A 6 13 14E A, C 4 6 14F B 6 8 16G D,E,F 2 5 8Identify the critical path. How much slack time is associated with each noncritical activity?Suppose you wanted to have 99% confidence in the project finishing on time. How manyweeks in total would your project team need to achieve this 99% likelihood?Memorial College is considering building a new multipurpose athletic complex on campus. The following activities would have to be undertaken before construction can begin. Activity Description ImmediatePredecessor Time(weeks) A Survey building site 7 B Develop initial design 10 C Obtain board approval A, B 13 D Select architect C 3 E Establish budget C 5 F Finalize design D, E 14 G Obtain financing E 11 H Hire contractor F, G 9 (a) Draw a project network. (b) Identify the critical path. (c) Develop the activity schedule for the project. Activity EarliestStart LatestStart EarliestFinish LatestFinish Slack A B C D E F G H (d) What is the expected completion time for the project? The expected completion time is weeks
- 3.1 Draw an Activity-On-Arrow (AOA) network diagram representing the project. Put the nodenumbers in circles and draw arrows from node to node, labelling each arrow with theactivity letter and estimated duration. 3.2 Identify all the paths on the network diagram and note how long they are. 3.3 What is the critical path for this project and how long is it? 3.4 What is the shortest possible time needed to complete the project?4. How long can activity C be delayed without delaying the whole project? 5. What is the purpose of PERT/CPM? How is it used in the industry?Please provide Handwritten answer. Computer Science Explain A project manager has facilitated the decomposition of work packages into activities. She next carries the team through several exercises to identify predecessor and successor activities. The project manager is performing activities associated with which process? 1. Plan Schedule Management 2. Define Activities 3. Sequence Activities 4. Estimate Activity Durations