Activity Time Required (weeks) A: Obtain site approval 4 B: Begin site excavation C: Place and secure gasoline tanks D: Install gasoline pumps E: Connect and test gasoline pumps F: Construct service area 2 1 1 2 G: Install and connect water and air compressor H: Test compressor I: Construct main building including the restrooms, the office, and the cash register area J: Install plumbing and electrical connections in the main building K: Cover tanks and surface the area L: Clean site M: Erect station signs 3 1 5 3 4 2 1

Understanding Business
12th Edition
ISBN:9781259929434
Author:William Nickels
Publisher:William Nickels
Chapter1: Taking Risks And Making Profits Within The Dynamic Business Environment
Section: Chapter Questions
Problem 1CE
icon
Related questions
icon
Concept explainers
Topic Video
Question

Two brothers have purchased a small lot, in the center of town, where they intend to build a gas station. The station will have two pumps, a service area for water and tire maintenance, and a main building with restrooms, office, and cash register area. Before they begin excavating the site, the local authorities must approve the location for a gasoline station and be certain that the placement of the storage tanks will not interfere with water, gas, and electric lines that are already in place.
Once the site has been approved, the excavation can begin. After excavation, the three primary parts of the construction can begin: laying in the gasoline tanks, building the water and tire service area (including installation of the air compressor), and constructing the main building. The surfacing can begin after all building is completed. After surfacing, the site must be cleaned and the station’s signs erected. However, before the station can open for business, the air compressor must be inspected, tested, and approved.
The activities and the time required for each of them are as follows: (given)

a. Based on the description of the project, determine the activity precedence relationships and develop a network for the project.
b. Determine the critical path and the earliest and the latest starting and finishing times for each activity.
c. Draw the Gantt chart for this project based on earliest times.
d. Suppose that the air compressor fails to function correctly and must be replaced. It takes two weeks to obtain another compressor and test it. Will the project necessarily be delayed as a result?
e. List the activities that must be completed by the end of the 15th week in order to guarantee that the project is not delayed.
f. Solve this problem using linear programming.

 

Activity
Time Required (weeks)
A: Obtain site approval
4
B: Begin site excavation
C: Place and secure gasoline tanks
D: Install gasoline pumps
E: Connect and test gasoline pumps
F: Construct service area
2
1
1
2
G: Install and connect water and
air compressor
H: Test compressor
I: Construct main building including the
restrooms, the office, and the cash register area
J: Install plumbing and electrical connections
in the main building
K: Cover tanks and surface the area
L: Clean site
M: Erect station signs
3
1
5
3
4
2
1
Transcribed Image Text:Activity Time Required (weeks) A: Obtain site approval 4 B: Begin site excavation C: Place and secure gasoline tanks D: Install gasoline pumps E: Connect and test gasoline pumps F: Construct service area 2 1 1 2 G: Install and connect water and air compressor H: Test compressor I: Construct main building including the restrooms, the office, and the cash register area J: Install plumbing and electrical connections in the main building K: Cover tanks and surface the area L: Clean site M: Erect station signs 3 1 5 3 4 2 1
Expert Solution
steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Understanding Business
Understanding Business
Management
ISBN:
9781259929434
Author:
William Nickels
Publisher:
McGraw-Hill Education
Management (14th Edition)
Management (14th Edition)
Management
ISBN:
9780134527604
Author:
Stephen P. Robbins, Mary A. Coulter
Publisher:
PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract…
Spreadsheet Modeling & Decision Analysis: A Pract…
Management
ISBN:
9781305947412
Author:
Cliff Ragsdale
Publisher:
Cengage Learning
Management Information Systems: Managing The Digi…
Management Information Systems: Managing The Digi…
Management
ISBN:
9780135191798
Author:
Kenneth C. Laudon, Jane P. Laudon
Publisher:
PEARSON
Business Essentials (12th Edition) (What's New in…
Business Essentials (12th Edition) (What's New in…
Management
ISBN:
9780134728391
Author:
Ronald J. Ebert, Ricky W. Griffin
Publisher:
PEARSON
Fundamentals of Management (10th Edition)
Fundamentals of Management (10th Edition)
Management
ISBN:
9780134237473
Author:
Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:
PEARSON