An activity with budgeted cost of 2000 JD, the percent complete of this activity is 50% to date. if actual cost of performed work is 900 JD. The cost variance (CV) is
Q: Qf#4 Cost estimation plays a vital role in the success of any project. Explain the different tools…
A: Cost estimation is predicted amount of the money that is to be spend on the project. It's evaluation…
Q: From the following table, develop network diagram, determine the critical path, and Calculate the…
A: Given:- The activity and duration of the activity is given To determine:- The critical path The…
Q: 4. Calculate ES, EF, LS, LF, TF, FF for each activity, determine the project duration and critical…
A: Done using Forward and Backward pass method
Q: Normal Crash Task Precedence Duration Cost Duration Cost Name (week) (week) A 0,1 700 3 850 В 100…
A: Solution Since you have posted a question with multiple sub-parts, we will solve three sub-parts for…
Q: An investor is considering buying some land for $100,000 and constructing an office building on it.…
A: total cost of building A = 100,000+500,000 = 600,000 revenue from building A = 200,000+(70,000 x 20)…
Q: 1. Determine the normal duration of the project 2. Determine the normal cost of the project
A: Given Data:
Q: Q.2 From the following table, develop network diagram, determine the critical path, and Calculate…
A:
Q: A : The number of procedures followed to reduce the duration of the project
A: The total duration of the project depends on every small work in the project. The project cost also…
Q: activities A1, A2, A3, A4, A5, A6, A7, A8, A9, and A10 sł durations provided under each activity.…
A: We need to determine Total Time of Project ES=Earliest Start Time EF=Earliest Finish Time LS=Least…
Q: Activity Precedes M G, H, K G 2. Prepare an arrow diagram to link activities H B for the project…
A: The activities of the given project are as given below: Activity Precedes M G, H, K G A H B…
Q: From the following data, develop an optimum time cost plan assuming that the indirect cost is…
A:
Q: If BCWP is 320 $ and the ACWP is 500$ then you are probably: Select one: O a. On Budget O b. Under…
A:
Q: Construction safety and health planning is very important in order to achieve project success. This…
A:
Q: The following bar chart shows the activities to complete a project in 6 months (each column…
A: Total cost is 1480ACWP=$490BCWP=100+200+60+40+75=$475BCWS=100+200+60+80+40+150=$630
Q: Q6: A construction project will have a Base cost of $3,250,000. There is a 5 percent chance that the…
A: Part A Incentive of finishing ahead is the contingency reserve = $40,000 Part C Best case scanerio…
Q: A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes…
A: Given data- optimistic time to=6 minutespessimistic time tp=60 minutesaverage time tm=15 minutesTo…
Q: Draw bar chart for activities for a house construction project
A: Bar chart or Gantt chart is the activity chart on which we plot the activity with the required…
Q: A construction company has an opportunity to submit a bid for the construction of a new apartment…
A: Hi! Thank you for the question, As per the honour code, we are allowed to answer three sub-parts at…
Q: ratio
A: PERT uses three estimated times for activity duration optimistic time The estimate is determined…
Q: Q6: Perform PDM calculations for the small project below and determine activity times. Durations are…
A:
Q: EXERCISES: 1- Consider the following data of a project. Activity Predecessor(s) Duration (weeks) 3.…
A: As per our company guidelines we are supposed to answer only first 3 sub-parts. Kindly repost other…
Q: Q2) Prepare a time schedule for the construction for 80 houses using line of balance technique…
A: :
Q: Financial data of a highway construction project is given below. You are quest such that both cost…
A:
Q: c) Briefly discuss the key items that must be considered in estimating the hourly rate fo r…
A: Estimation of hourly rate for construction plant
Q: Problem 2: An engineering student has only 45 minutes before the final exam in her Engineering…
A: The given data is: Time before exam = 45 minutes. She can use only one method of assistance.…
Q: Draw the node diagram and perform the CPM computations for the schedule shown. Tabulate ES, EF, LS,…
A: The critical path is given as ;
Q: Q2: Consider the following table summarizing the details of a project: Duration (weeks) Most likely…
A: As per our company guidelines we are supposed to answer only first 3 sub-parts. Kindly repost other…
Q: Q3: For the project data in the table below. Answer the following questions: a) Draw an AOA network…
A:
Q: Assume the following project data given in Table 1. It is required to crash the project duration…
A: Given- Indirect cost= LE100
Q: Q2(b)(ii) Resource constraint has affected the project in so many ways. Describe how has slack…
A: Program evaluation and review technique: It is a tool to visualize a diagrammatical timeframe of a…
Q: Q4/ The table below shows the duration and direct costs for the activities of a construction…
A:
Q: For the same problem, if the owner has the following resources constraints of 7 resources/day: Daily…
A: To find duration of activities using resource allocation
Q: project your firm is considering for implementation has these estimated costs and revenues: an…
A: Present value is the current value of the future sum of money, at a specified rate of return. The…
Q: storey residential project, make a logical arrangement of activities by filling out the column for…
A: Step: 1 Critical path method (CPM): - It is defined as the longest path or shortest duration in…
Q: The activity-on-arrow network of activities for a construction project is shown in the figure. The…
A: Given AON diagram, TO find the critical duration for the project
Q: Q4) Using the time-cost trade-off concepts, determine the logical steps to reduce the following…
A:
Q: For the information of project shown in table below: 1. Draw the network diagram by using AOA…
A:
Q: Q3: The construction plan for a house is shown in figure and table below, gives the manhoures…
A:
Q: Assume the following project data given in Table 2. It is required to crash the project duration…
A: One important aspect of project management is looking at ways of reducing the overall project time…
Q: 10. Given the diagrams in Figure P5.1 of progress on individual work pack- ages of a project, answer…
A: Given Data : BCWS = budget cost of work scheduled (planned value) ACWP = Actual Cost of Work…
Q: The earned value report of a construction project shows that the cost performance index is 1.1. In…
A: we have relations:CV=BCWP-ACWPSV=BCWP-BCWSCPI=BCWPACWP
Q: Question: Discuss the relationship between the design of a project solution and long-term…
A: Solution: The design of a project is always performed in such a way that it benefits the present and…
Q: 2/ For the project data shown in the table below. If it was decided to turn over the project at 34…
A: The expected time of the activity, te=to+4×tm+tp6 The standard deviation of the activity,…
Q: What do you understand about the Level of Service (LOS)? Define briefly the six common terms related…
A: Level of service (LOS): Level of service (LOS) is a qualitative measure used to relate to the…
Q: PERT calculations indicate that duration of a given project is 72 weeks. With the variance of 15,…
A:
Q: To find the earned value (EV) of a project, the percentage of work complete is multiplied by the O…
A: Given data Earned value Percentage of work complete
Q: According to my answers, there is no impact of the owner's resources constraints on the activities'…
A: If a owner has resources constraints like budget related and manpower related, the progress of work…
Q: Project Z has a current budget of $20 million. The project is working on a 20-month schedule. After…
A: Giver AC =$6,5 million; PV = $6.8 million; EV = $7.1 million; Current butget = $ 20 million;
Step by step
Solved in 2 steps
- Compute the equivalent rate of 6% compounded semi-annually to a rate compounded quarterly. engineering econb) For the selected site, how much profit can be made if it is paid P362.25 per cubic meter delivered to the job site? Sol’n to bREVENUE = ?PROFIT = ?Question: a. Compute the overhaul volume. b. Compute the length of overhaul if total cost of hauling is P105,750.00 c. Compute the total cost of borrow.
- NHA plans to construct road (50 km + 135)for comfortable mobilization. There are two options available:a) spend PKR 15 billion now to construct 14 m wide carriageway, and widen it to 21 m in 15 years for PKR 18 billion more,b) construct 21 m wide road now for PKR 21 billion. Propose suitable alternative for above project by considering normal inflation while taking analysis period of 35 years, Interest is 6% and ignore maintenance costs.Pls. Answer, I'll rateCalculate the levels of these points (with an audit of calculations)
- Engineer Layla purchased a dump truck worth P850,000. She added P50,000for the delivery and other expenses. The said equipment is expected to be useful for 10 years. At the end of its life, it will cost x% of the first cost. Using SLM, its book value at year 5 is P517,500. What is the value of x?given the following data of cut and fill, compute the free haul distance, overhaul distance, waste and borrow volume. having the values of: Cost of overhaul: 3000 ID/station Cost of free haul: 5000 ID/cu.m Cost of borrow: 15000 ID/cu.m Free haul distance (F.H.D.): 300m = 2 stations Cost of waste=5000 ID/cu.m economic overhaul distance=5 stations limit of economic haul=8 stationsSolve this economic
- In the original RedBrand problem, the costs forshipping from plants or warehouses to customer 2were purposely made high so that it would be optimalto ship to customer 1 and then let customer 1 ship tocustomer 2. Use SolverTable appropriately to do thefollowing. Decrease the unit shipping costs from plantsand warehouses to customer 1, all by the same amount,until it is no longer optimal for customer 1 to ship to customer 2. Describe what happens to the optimal shipping plan at this point.Estimate settlement for A and E after 1 yearA silo consists of a right circular cylinder surmounted by a hemisphere. Find themost economical proportions for the silo, if the walls cost Php 3/sq in, the floorcosts Php 9 /sq in and the roof costs Php 12/sq in.