Assume that the number of days it takes a home builder to complete a house is normally distributed with an average completion time of 176.7 days and a standard deviation of 24.8 days. Calculate the probability that it will take between 185 and 225 days to complete the next home. Select one: a. 0.3451 O b. 0.2032 c. 0.3516 O d. 0.3477

Glencoe Algebra 1, Student Edition, 9780079039897, 0079039898, 2018
18th Edition
ISBN:9780079039897
Author:Carter
Publisher:Carter
Chapter10: Statistics
Section10.5: Comparing Sets Of Data
Problem 14PPS
icon
Related questions
Topic Video
Question

18

Assume that the number of days it takes a home builder to complete a
house is normally distributed with an average completion time of 176.7
days and a standard deviation of 24.8 days. Calculate the probability
that it will take between 185 and 225 days to complete the next home.
Select one:
O a. 0.3451
O b. 0.2032
O c. 0.3516
O d. 0.3477
Transcribed Image Text:Assume that the number of days it takes a home builder to complete a house is normally distributed with an average completion time of 176.7 days and a standard deviation of 24.8 days. Calculate the probability that it will take between 185 and 225 days to complete the next home. Select one: O a. 0.3451 O b. 0.2032 O c. 0.3516 O d. 0.3477
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Discrete Probability Distributions
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, probability and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Glencoe Algebra 1, Student Edition, 9780079039897…
Glencoe Algebra 1, Student Edition, 9780079039897…
Algebra
ISBN:
9780079039897
Author:
Carter
Publisher:
McGraw Hill