Bramble Construction Company began work on a $415,000 construction contract in 2020. During 2020, Bramble incurred costs of $268,500, billed its customer for $230,000, and collected $181,500. At December 31, 2020, the estimated additional costs to complete the project total $154,135. Prepare Bramble's journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed- contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No entry" for the account titles and enter O for the amounts. Round answers to 0 decimal places, e.g. 5,275.) No. Account Titles and Explanation (a) (b) Debit Credit

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 25E: Koolman Construction Company began work on a contract in 2019. The contract price is 3,000,000, and...
icon
Related questions
Question

Dinesh bhai 

Bramble Construction Company began work on a $415,000 construction contract in 2020. During 2020, Bramble incurred costs of
$268,500, billed its customer for $230,000, and collected $181,500. At December 31, 2020, the estimated additional costs to
complete the project total $154,135.
Prepare Bramble's journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-
contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required,
select "No entry" for the account titles and enter O for the amounts. Round answers to 0 decimal places, e.g. 5,275.)
No. Account Titles and Explanation
(a)
(b)
Debit
Credit
Transcribed Image Text:Bramble Construction Company began work on a $415,000 construction contract in 2020. During 2020, Bramble incurred costs of $268,500, billed its customer for $230,000, and collected $181,500. At December 31, 2020, the estimated additional costs to complete the project total $154,135. Prepare Bramble's journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed- contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No entry" for the account titles and enter O for the amounts. Round answers to 0 decimal places, e.g. 5,275.) No. Account Titles and Explanation (a) (b) Debit Credit
Expert Solution
steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
Individual Income Taxes
Individual Income Taxes
Accounting
ISBN:
9780357109731
Author:
Hoffman
Publisher:
CENGAGE LEARNING - CONSIGNMENT
SWFT Individual Income Taxes
SWFT Individual Income Taxes
Accounting
ISBN:
9780357391365
Author:
YOUNG
Publisher:
Cengage
SWFT Comprehensive Vol 2020
SWFT Comprehensive Vol 2020
Accounting
ISBN:
9780357391723
Author:
Maloney
Publisher:
Cengage