Carrie Construction (CC) is a company specializing in building airport runways and major highways. As a part of its business, it receives supplies of aggregate (stone, sand, gravel, and so on) from two suppliers: Austin Aggregate and Granger Materials. The CC purchasing department has a preference for buying from Granger based on price but occasionally has to order from Austin when Granger cannot fill the order. Carrie Construction has recently had problems with the quality and the timeliness of deliveries. When a supplier delivers a load to CC, it goes through an initial inspection to assure it meets specification. If the load fails the initial inspection, it goes through a secondary inspection to determine the exact issue. Almost always, the issue can be resolved and the load can be used. The initial inspection costs $3,000 per load. A secondary inspection, which is more thorough, costs $15,000 per load. If a delivery is delayed, Carrie has to hire temporary workers or pay overtime to some employees. The average cost of a delayed load is $6,000. The following are summary statistics from last year's purchases from the two suppliers:   Granger Materials Austin Aggregate Number of loads 600 150 Average tons per load 5,000 10,000 Average price per ton $ 7.20 $ 8.00 Number of initial inspections passed 450 141 Number of delayed deliveries 120 15 Required: Calculate the effective cost of a ton of aggregate from the two suppliers, assuming that last year's experience is representative. Note: Round "Average effective cost per ton" answers to 2 decimal places.

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter6: Activity-based, Variable, And Absorption Costing
Section: Chapter Questions
Problem 5EB: Identify appropriate cost drivers for these cost pools: A. material cost pool B. machine cost pooi...
icon
Related questions
Question

Carrie Construction (CC) is a company specializing in building airport runways and major highways. As a part of its business, it receives supplies of aggregate (stone, sand, gravel, and so on) from two suppliers: Austin Aggregate and Granger Materials. The CC purchasing department has a preference for buying from Granger based on price but occasionally has to order from Austin when Granger cannot fill the order.

Carrie Construction has recently had problems with the quality and the timeliness of deliveries. When a supplier delivers a load to CC, it goes through an initial inspection to assure it meets specification. If the load fails the initial inspection, it goes through a secondary inspection to determine the exact issue. Almost always, the issue can be resolved and the load can be used. The initial inspection costs $3,000 per load. A secondary inspection, which is more thorough, costs $15,000 per load. If a delivery is delayed, Carrie has to hire temporary workers or pay overtime to some employees. The average cost of a delayed load is $6,000.

The following are summary statistics from last year's purchases from the two suppliers:

  Granger Materials Austin Aggregate
Number of loads 600 150
Average tons per load 5,000 10,000
Average price per ton $ 7.20 $ 8.00
Number of initial inspections passed 450 141
Number of delayed deliveries 120 15

Required:

Calculate the effective cost of a ton of aggregate from the two suppliers, assuming that last year's experience is representative.

Note: Round "Average effective cost per ton" answers to 2 decimal places.

Item
Total tons purchased
Total purchase price
Initial inspection costs
Secondary inspection costs
Delay costs
Total costs
Average effective cost per ton
Granger
Materials
Austin
Aggregate
Transcribed Image Text:Item Total tons purchased Total purchase price Initial inspection costs Secondary inspection costs Delay costs Total costs Average effective cost per ton Granger Materials Austin Aggregate
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Relevant cost analysis
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College