Compute the expected activity completion times and the variance for each activity

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%
The following estimates of activity times (in days) are available for a small project.
Activity
Optimistic
Most Probable
Pessimistic
A
6.0
7
B
10.0
11
C
8.5
12.5
D
10.0
11
8.0
10
F
3
4.0
5
(a) Compute the expected activity completion times and the variance for each activity. (Round your answers to two decimal places.)
Expected
Activity
Variance
Times
A
(b) An analyst determined that the critical path consists of activities B-D-F. Compute the expected project completion time and the variance of this path. (Round your answers to two decimal places.)
expected project completion time
variance of projection completion time
Transcribed Image Text:The following estimates of activity times (in days) are available for a small project. Activity Optimistic Most Probable Pessimistic A 6.0 7 B 10.0 11 C 8.5 12.5 D 10.0 11 8.0 10 F 3 4.0 5 (a) Compute the expected activity completion times and the variance for each activity. (Round your answers to two decimal places.) Expected Activity Variance Times A (b) An analyst determined that the critical path consists of activities B-D-F. Compute the expected project completion time and the variance of this path. (Round your answers to two decimal places.) expected project completion time variance of projection completion time
Davison Construction Company is building a luxury lakefront home in the Finger Lakes region of New York. Coordination of the architect and subcontractors will require a major effort to meet the 46-week completion date
requested by the owner. The Davison project manager prepared the following project network.
B
F
H
Start
A
G
Finish
D
E
Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows.
Activity
Optimistic
Most Probable
Pessimistic
A
4
8
12
B
6
6
12
18
D
7
E
6
18
F
5
17
G
10
15
20
H
5
6
13
(a) Find the critical path. (Enter your answers as a comma-separated list.)
(b) What is the expected project completion time (in weeks)?
weeks
(c) Based only on the critical path, what is the estimated probability the project can be completed in 46 weeks as requested by the owner? (You may need to use the appropriate technology to answer this question. Round
your answer to four decimal places.)
(d) Based only on the critical path, what is the estimated probability the building project could run more than 3 months late? Use 59 weeks for this calculation. (You may need to use the appropriate technology to answer
this question. Round your answer to four decimal places.)
in
Transcribed Image Text:Davison Construction Company is building a luxury lakefront home in the Finger Lakes region of New York. Coordination of the architect and subcontractors will require a major effort to meet the 46-week completion date requested by the owner. The Davison project manager prepared the following project network. B F H Start A G Finish D E Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows. Activity Optimistic Most Probable Pessimistic A 4 8 12 B 6 6 12 18 D 7 E 6 18 F 5 17 G 10 15 20 H 5 6 13 (a) Find the critical path. (Enter your answers as a comma-separated list.) (b) What is the expected project completion time (in weeks)? weeks (c) Based only on the critical path, what is the estimated probability the project can be completed in 46 weeks as requested by the owner? (You may need to use the appropriate technology to answer this question. Round your answer to four decimal places.) (d) Based only on the critical path, what is the estimated probability the building project could run more than 3 months late? Use 59 weeks for this calculation. (You may need to use the appropriate technology to answer this question. Round your answer to four decimal places.) in
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.