Compute the expected time and variance for each activity. What is the critical path and the expected duration of the project? What is the probability that the project will take longer than 58 days to complete?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question
  1. Compute the expected time and variance for each activity.
  2. What is the critical path and the expected duration of the project?
  3. What is the probability that the project will take longer than 58 days to complete?
You are asked to manage an upcoming project for a client based in Chicago. Your supervisor, Susan, asked you to
determine if the project will be completed in 2 months (60 days). Susan sent you the estimated time durations (in
days) for the project. The information is given below:
Activity
Immediate
Optimistic
Most Likely
Pessimistic
Predecessor
Time
Time
Time
A
10
12
15
В
A
6
10
14
C
A
10
15
20
D
A
9.
9.
18
E
В
5
8
F
C,E
10
12
13
G
12
14
16
H
B,D
18
21
24
I
B,D
10
15
20
J
F.G.H
8.
10
14
Transcribed Image Text:You are asked to manage an upcoming project for a client based in Chicago. Your supervisor, Susan, asked you to determine if the project will be completed in 2 months (60 days). Susan sent you the estimated time durations (in days) for the project. The information is given below: Activity Immediate Optimistic Most Likely Pessimistic Predecessor Time Time Time A 10 12 15 В A 6 10 14 C A 10 15 20 D A 9. 9. 18 E В 5 8 F C,E 10 12 13 G 12 14 16 H B,D 18 21 24 I B,D 10 15 20 J F.G.H 8. 10 14
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.