Consider a project with seven tasks. Three tasks - tasks 3, 4, and 5 - require a specific resource for completion; all needed resources must be available at the site before a task can be started. Task Duration Predecessor (s) Units of Value of Resource Completed Task Needed 3 1 3 1 10 $4000 3 10 S3000 5 3 12 $5000 6. 4 7 2, 5,6 Each resource unit cost S100; no quantity discounts are available. In addition, it costs $2 per unit per time period to hold this resource in stock, and it costs $45 just to place an order for materials (independent of the number of units ordered). When should each task in the project be started and when and how many resources should be ordered to minimize total project costs? 2. en 1, 2.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter8: Evolutionary Solver: An Alternative Optimization Procedure
Section: Chapter Questions
Problem 36P
icon
Related questions
Question
Consider a project with seven tasks. Three tasks – tasks 3, 4, and 5 – require a specific resource for
completion; all needed resources must be available at the site before a task can be started.
Task
Duration
Predecessor (s)
Units of
Value of
Resource
Completed
Task
Needed
3
3
10
$4000
3
1
10
S3000
3
12
$5000
1
4
7
2, 5,6
Each resource unit cost $100; no quantity discounts are available. In addition, it costs $2 per unit
per time period to hold this resource in stock, and it costs $45 just to place an order for materials
(independent of the number of units ordered). When should each task in the project be started
and when and how many resources should be ordered to minimize total project costs?
1.
1,
en
en
1.
2.
en
Transcribed Image Text:Consider a project with seven tasks. Three tasks – tasks 3, 4, and 5 – require a specific resource for completion; all needed resources must be available at the site before a task can be started. Task Duration Predecessor (s) Units of Value of Resource Completed Task Needed 3 3 10 $4000 3 1 10 S3000 3 12 $5000 1 4 7 2, 5,6 Each resource unit cost $100; no quantity discounts are available. In addition, it costs $2 per unit per time period to hold this resource in stock, and it costs $45 just to place an order for materials (independent of the number of units ordered). When should each task in the project be started and when and how many resources should be ordered to minimize total project costs? 1. 1, en en 1. 2. en
Expert Solution
steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,