Daily cells for a landfill are operated so that the following conditions are maintained: thickness of daily cover= 0.2 m; slope (horizontal:vertical)= 3:1, working face for refuse= 30 m; height of refuse= 3 m; and volume of daily refuse= 1,800 m^3/day. The landfill is interested in reducing requirements for daily cover soil over its 20 year life and is considering three options (that is, have a lower Vs/Vr). Which option should be the best? Why?

Solid Waste Engineering
3rd Edition
ISBN:9781305635203
Author:Worrell, William A.
Publisher:Worrell, William A.
Chapter8: Landfills
Section: Chapter Questions
Problem 8.2P
icon
Related questions
Question

 Daily cells for a landfill are operated so that the following conditions are maintained: thickness of daily cover= 0.2 m; slope (horizontal:vertical)= 3:1, working face for refuse= 30 m; height of refuse= 3 m; and volume of daily refuse= 1,800 m^3/day. The landfill is interested in reducing requirements for daily cover soil over its 20 year life and is considering three options (that is, have a lower Vs/Vr). Which option should be the best? Why?
Option 1: Increase height of refuse to 4 m.
Option 2: Increase daily refuse volume to 2000 m3/day.
Option 3: Decrease working face to 20 m. 

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 6 steps

Blurred answer
Knowledge Booster
Landfills
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Solid Waste Engineering
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,