Question

Determine the probability that the project will take longer than 50 weeks

 

Duration in weeks
Activity
Proceeding activity Optimistic
Most likely
Pessimistic
A
3
3
10
12
15
4
В
E
A, D
3
3
3
В
3
4
5
G
С, Е, F
8
10
20
H
2
3
G
2
2
H
4
10
K
I, J
4
6.
5.
2.
2.
Transcribed Image Text:Duration in weeks Activity Proceeding activity Optimistic Most likely Pessimistic A 3 3 10 12 15 4 В E A, D 3 3 3 В 3 4 5 G С, Е, F 8 10 20 H 2 3 G 2 2 H 4 10 K I, J 4 6. 5. 2. 2.
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Sample space, Events, and Basic Rules of Probability
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, probability and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Linear Algebra: A Modern Introduction
Linear Algebra: A Modern Introduction
Algebra
ISBN:
9781285463247
Author:
David Poole
Publisher:
Cengage Learning
Glencoe Algebra 1, Student Edition, 9780079039897…
Glencoe Algebra 1, Student Edition, 9780079039897…
Algebra
ISBN:
9780079039897
Author:
Carter
Publisher:
McGraw Hill