Develop a network drawing for Hill Construction, and determine the critical path(s). Assess the length of the project expected to take.  Calculate the probability of finishing in 270 days.  If it were necessary to crash to 250 or 240 days, analyse whether Hill would do it so and calculate costs that it is willing to bear in this project. As noted in the case, assume that optimistic time estimates can be used as crash times.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%

After six months of study, much political arm wrestling, and some serious financial analysis, Dr  Martin Starr, president of Southwestern University, had reached a decision. To the delight of its students and to the disappointment of its athletic boosters, SWU would not be relocating to a new football site but would expand the capacity at its on-campus stadium.

Adding 21,000 seats, including dozens of luxury skyboxes, would not please everyone. The influential football coach, Billy Bob Taylor, had long argued the need for a first-class stadium, one with built-in dormitory rooms for his players and a palatial office appropriate for the coach of a future NCAA champion team. But the decision was made, and everyone, including the coach, would learn to live with it.

The job now was to get construction going immediately after the current season ended. This would allow exactly 270 days until the upcoming season opening game. The contractor, Hill Construction (Bob Hill being an alumnus, of course), signed the contract. Bob Hill looked at the tasks his engineers had outlined and looked President Starr in the eye. “I guarantee the team will be able to take the field on schedule next year,” he said with a sense of confidence. “I sure hope so,” replied Starr. “The contract penalty of $10,000 per day for running late is nothing compared to what Coach Billy Bob Taylor will do to you if our opening game with Penn State is delayed or cancelled.” Hill, sweating slightly, did not respond. In football-crazy Texas, Hill Construction’s name would be mud if the 270-day target were missed.

Back in his office, Hill again reviewed the data. (refer to the table below, and note that optimistic time estimates can be used as crash times.) He then gathered his foremen. “People, if we’re not 75% sure we’ll finish this stadium in less than 270 days, I want this project crashed! Give me the cost figures for a target date of 250 days—also for 240 days. I want to be early, not just on time!”

 

Time (Days)

 

Activity

Description

Immediate predecessors

Optimistic

Most likely

Pessimistic

Crash cost/day (RM)

A

Bonding, insurance, tax structuring

-

20

30

40

1,500

B

Foundation, concrete footings for boxes

A

20

65

80

3,500

C

Upgrading  skyboxes, stadium seating

A

60

60

100

4,000

D

Upgrading walkways, stairwells, elevators

C

30

50

100

1,900

E

Interior wiring, lathes

B

25

30

35

9,500

F

Inspection approvals

E

1

1

1

0

G

Plumbing

D, E

25

30  

35

2,500

H

Painting

G

10

20

30

2,000

I

Hardware/air conditioning/metal workings

H

20

25

60

2,000

J

Tile/carpeting/windows

H

8

10

12

6,000

K

Inspection

J

1

1

1

0

L

Final detail work/clean-up

I, K

20

25

60

4,500

 

Required:

  1. Develop a network drawing for Hill Construction, and determine the critical path(s). Assess the length of the project expected to take. 
  2. Calculate the probability of finishing in 270 days. 
  3. If it were necessary to crash to 250 or 240 days, analyse whether Hill would do it so and calculate costs that it is willing to bear in this project. As noted in the case, assume that optimistic time estimates can be used as crash times. 
Expert Solution
steps

Step by step

Solved in 6 steps with 8 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.