Draw a network diagram representing the sequence of activities and the dependence between them. Determine how long it will take to complete the job by conducting the forward pass By conducting the backward pass, identify the critical path and the non- critical path(s).

icon
Related questions
Question
100%
A plumber has decided to use the techniques of project management
in order to plan a job. He knew all the different activities of the job,
their precedence and their average durations. They are shown on the
table below.
Preceding
activities
Activity
Duration
(days)
3
None
None
B
4
C
7
E
B and C
Required:
1. Draw a network diagram representing the sequence of activities
and the dependence between them.
2. Determine how long it will take to complete the job by conducting
the forward pass
3. By conducting the backward pass, identify the critical path and the
non- critical path(s).
Transcribed Image Text:A plumber has decided to use the techniques of project management in order to plan a job. He knew all the different activities of the job, their precedence and their average durations. They are shown on the table below. Preceding activities Activity Duration (days) 3 None None B 4 C 7 E B and C Required: 1. Draw a network diagram representing the sequence of activities and the dependence between them. 2. Determine how long it will take to complete the job by conducting the forward pass 3. By conducting the backward pass, identify the critical path and the non- critical path(s).
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
Highway surveys and location
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.