Question

draw the network diagram

2. Given the data, answer the questions below.
Activity
Normal Time
Normal Cost
Crashed Time
Crashed Cost
(weeks)
(Pesos)
50,000
35,000
70,000
(weeks)
12
(Pesos)
30,000
1-2
7
2-3
8
20,000
40,000
2-4
4
3-4
4-5
4
5,000
1
11,000
4-6
12
500,000
5,000
150,000
750,000
710,000
5-6
4
1
11,000
6-7
3
220,000
1,107,000
4
Transcribed Image Text:2. Given the data, answer the questions below. Activity Normal Time Normal Cost Crashed Time Crashed Cost (weeks) (Pesos) 50,000 35,000 70,000 (weeks) 12 (Pesos) 30,000 1-2 7 2-3 8 20,000 40,000 2-4 4 3-4 4-5 4 5,000 1 11,000 4-6 12 500,000 5,000 150,000 750,000 710,000 5-6 4 1 11,000 6-7 3 220,000 1,107,000 4
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,