During 2025, Ivanhoe Company started a construction job with a contract price of $1,610,000. The job was completed in 2027. The following information is available. Costs incurred to date Estimated costs to complete Billings to date Collections to date 2025 $383,800 626,200 302,000 271,000 2026 $905,280 198,720 896,000 817,000 2027 $1,063,000 -0- 1,610,000 1,419,000

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 26E
icon
Related questions
Question
Prepare all necessary journal entries for 2026. (Credit account titles are automatically indented when amount is entered. Do not indent
manually. If no entry is required, select "No Entry" for the account titles and enter O for the amounts. For costs incurred use account
Materials, Cash, Payables. List all debit entries before credit entries.)
Account Titles and Explanation
(To record cost of construction.)
(To record progress billings.)
(To record collections.)
Debit
Credit
Transcribed Image Text:Prepare all necessary journal entries for 2026. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter O for the amounts. For costs incurred use account Materials, Cash, Payables. List all debit entries before credit entries.) Account Titles and Explanation (To record cost of construction.) (To record progress billings.) (To record collections.) Debit Credit
During 2025, Ivanhoe Company started a construction job with a contract price of $1,610,000. The job was completed in 2027. The
following information is available.
Costs incurred to date
Estimated costs to complete
Billings to date
Collections to date
2025
$383,800 $905,280
626,200
302,000
2026
271,000
198,720
896,000
817,000
2027
$1,063,000
-0-
1,610,000
1,419,000
Transcribed Image Text:During 2025, Ivanhoe Company started a construction job with a contract price of $1,610,000. The job was completed in 2027. The following information is available. Costs incurred to date Estimated costs to complete Billings to date Collections to date 2025 $383,800 $905,280 626,200 302,000 2026 271,000 198,720 896,000 817,000 2027 $1,063,000 -0- 1,610,000 1,419,000
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
SWFT Comprehensive Volume 2019
SWFT Comprehensive Volume 2019
Accounting
ISBN:
9780357233306
Author:
Maloney
Publisher:
Cengage
SWFT Comprehensive Vol 2020
SWFT Comprehensive Vol 2020
Accounting
ISBN:
9780357391723
Author:
Maloney
Publisher:
Cengage
Individual Income Taxes
Individual Income Taxes
Accounting
ISBN:
9780357109731
Author:
Hoffman
Publisher:
CENGAGE LEARNING - CONSIGNMENT
SWFT Individual Income Taxes
SWFT Individual Income Taxes
Accounting
ISBN:
9780357391365
Author:
YOUNG
Publisher:
Cengage
SWFT Essntl Tax Individ/Bus Entities 2020
SWFT Essntl Tax Individ/Bus Entities 2020
Accounting
ISBN:
9780357391266
Author:
Nellen
Publisher:
Cengage