Eminem Company recognized gross profit of P720,000 on its long-term project which has accumulated costs of P2,880,000. To finish the project, the company estimates that it has to incur additional costs of P1,920,000. Determine the contract price.
Q: DMCI entered into a fixed price contract for the construction of a road for Camella Corp. DMCI…
A: The question is related to Construction Contracts. All cost that are directly attributable to the…
Q: Co. started work on an P8,000,000 fixed-price truction contract in 20x1. Information on the contract…
A: in case of construction contract it is important to understand the method of completion so fast in…
Q: Wynn, Inc. has a contract to construct a large hotel for P12,000,000. The contract was signed on…
A: Loss is incurred when the amount of total cost increases the amount of revenue. That excess of cost…
Q: Athena Co. started work on an P8M fixed-price construction contract in 20x1. Information on the…
A: The recognized profit or loss can be calculated by deducting the estimated cost to complete from…
Q: Tyro Construction Company has two projects, for which it reported, as of December 31, 20x5,…
A: Revenue to be recognized in 20x4 on Project A = Contract price x Percent completed = 4,800 x 75% =…
Q: ABC Co. started work on an P8,000,000 fixed-price construction contract in 20x1. Information on the…
A: Percent complete=Costs to dateCosts to date+Estimated costs to complete×100 Profit/(loss)…
Q: Indiana Co. began a construction project in 2021 with a contract price of $160 million to be…
A: Calculate the gross profit recognized in 2021. Working note: Calculate the percentage of…
Q: On January 1, Year 1, Crawford Construction Company enters into a contract with a customer to build…
A: Revenue to be recognised = Price * Percentage of completion
Q: The Naples Company uses the percentage-of-completion method and the cost-to-cost method for its…
A: Using percentage method, the gross profit recognized during the period on the basis of percentage of…
Q: In 20x1, ABC Co. was contracted to build a railroad. The contract price is equal to the total…
A: Given that, Contract price = Total cost + 25% Incentive to be paid= P200,000 Total cost incurred…
Q: In 2019, Richard Corp signed a contract valued at $1M. It was estimated that $750K would be required…
A:
Q: YEYE Company began operations on January 2, 2021. During the year, the company entered into a…
A: Percentage of Completion Method In the percentage of completion method the benefits which are…
Q: CONSTRUCTION COMPANY is executing a construction project, which is expected to take three years. The…
A: Marketing and selling costs are not included in the cost of construction because they cannot be…
Q: Sunshine Bhd. entered a contract to build a building for its customer with the agreed total price of…
A: Cost incurred during the year 2019 = $1,000,000 - $400,000 = $600,000 Cost incurred during the year…
Q: Indiana Co. began a construction project in 2021 with a contract price of $150 million to be…
A: Indiana Co. began a construction project in 2021 with a contract price of $150 million to be…
Q: The ETHAN Construction company was the lowest bidder on a specialized equipment contract. The…
A:
Q: ABC Corp. uses the cost to cost method to account for its construction contracts. The contract price…
A: Contract Accounting In the construction contract total cost which are incurred in the contract is…
Q: 7. On April 1, 2020, Waleed company entered into a cost- plus fixed-fee contract to construct a…
A: Formula: Total estimated project cost = Estimated project cost + Fixed fee in the contract. Sum of…
Q: Felix Ltd. uses the percentage-of-completion method to account for work performed on its contracts…
A: Price of contract = $ 3,000,000 Cost till date = $ 1,000,000 Total estimated cost = $ 1,750,000
Q: In 20x1, ABC Co. was contracted to build a railroad. The contract price is equal to the construction…
A:
Q: On March 31, 2018, Big Boats Company entered into a contract with Vacations Unlimited to produce a…
A: Total cost refers to of the expenses incurred to make an investment, which includes the cost of the…
Q: The ETHAN Construction company was the lowest bidder on a specialized equipment contract. The…
A: Computation of Gross profit 2017 Particular Cost already incurred 6,562,500 Cost to…
Q: A Construction Co. entered into a P80M fixed price contract for the construction of a private road.…
A:
Q: Tony Corporation has a construction contract in progress as follows : Total contract price: $550…
A: The question is related to the IFRS 15 "Revenue from Contracts with customers" or "Construction…
Q: Philip Construction Company started a project with a contract price of P80 million. The cost…
A: Under construction contracts, there are various methods of recognising costs and revenue during the…
Q: Excess Construction Corp. has a $16 million contract to construct a building. The company estimates…
A: Construction Contract - It is a legally binding agreement between two parties based on policies and…
Q: What is the percentage of completion of the contract as of the end of the first year? VALEDICTION…
A: Percentage of Completion Method in Contract work While using the percentage of completion method the…
Q: Tyro Construction Company has two projects, for which it reported, as of December 31, 20x5, the…
A: Revenue recognized in 20x4 = Contract Price x Percent completed in 20x4 = 480000 x 75% = P360000
Q: On July 1, 2021, Discipline Company obtained a contract to construct a building which is estimated…
A: Solution: Contract price when contract was entered into on July 1 2021 = Total billings to client +…
Q: On September 1, 20x1, ABC Co. enters into a contract with a customer to remodel a plant's electrical…
A: As per ASC 606, The input method (cost to cost method) used for calculating the profits has a…
Q: Indiana Co. began a construction project in 2018 with a contract price of $162 million to be…
A: Cost Accounting- It is branch of that ascertains cost associated with the production of certain…
Q: On 1 October 20X2 Pricewell entered into a contract to construct a bridge over a river. The total…
A: We have the following information: The total contract revenue was $50 million and construction is…
Q: ABC Co. started work on an P8,000,000 fixed-price construction contract in 20x1. Information on the…
A: The construction profit can be recognized on the basis of percentage of the work completed during…
Q: PIA Company began operations on January 2, 2021. During the year, the company entered into a…
A: Solution: % completion during the year = Cost incurred during the year / Total estimated costs =…
Q: [A] The franchisor will initially recognize P20,000 contract asset. [B] The franchisor will…
A: Franchise Agreement To recognize the revenue in the franchise agreement either in the point of time…
Q: The Heart Co. has just completed a 4-year contract to which the following relate: Labor and…
A: As per IFRS 15, Revenue from contract with customer Total contract cost includes contract…
Q: Rogers Ltd. has entered into a contract beginning in February 2020 to build two warehouses for ocean…
A: The question is based on the concept of Financial Accounting. As per the Bartleby guidelines we are…
Q: Tony Corporation has a construction contract in progress as follows : Total contract price: $550…
A: Percentage of completion method recognizes the incomes and expenses related to the percentage of…
Q: Batanes Construction Company recognized gross loss of P78,000 on its long-term project which has…
A: The contract price is the total of estimated costs and estimated gross profits for the contract.
Q: Mediocre Inc. has entered into a very profitable fixed price contract for constructing a high-rise…
A: A construction contract is a mutual agreement between two parties based on terms and conditions…
Q: For a construction firm using the cost recovery method, if costs exceed billings ons some contracts…
A: Current asset = Cost incurred - billing made Current liability = Billing made - cost incurred
Q: atanes Construction Company recognized gross loss of P78,000 on its long-term project which has…
A: Total cost=Accumulated cost+Additional cost=P 595,000+P 820,000=P 1,415,000
Q: On March 1, 2021, AST Corporation contracted to build two buildings for a total contract price of…
A: Solution: Lumpsum price allocated to Building no 1 = P27*20 / 30 = P18 M
Q: The Naples Company uses the overtime/percentage-of-completion method and the point in-…
A: Using percentage of completion method, the gross profit recognized on the basis of percentage of the…
Q: Franklin Construction entered into a fixed-price contract to build a freeway-connecting ramp for $30…
A: Following are the calculation of gross profit or loss recognized in 1st year if recognize revenue…
Q: On September 1, 20x1, ABC Co. enters into a contract with a customer to remodel a plant's electrical…
A: Contract costing is a method of job costing used for large undertakings that take a long time to…
Q: For a construction firm using the cost recovery method, if costs exceed billings on some contracts…
A: Current asset = Cost incurred - billing made Current liability = Billing made - cost incurred
Q: At that time, Andrei estimated that it would take 3 y at a total cost of P4,500,000. The total…
A: a. First we need to compute the contract liability based on Completed-contract method. For that…
Q: How much is the profit recognized in 20x2?
A: The company is using cost to cost method to measure its contract progress. Equation for % of…
Eminem Company recognized gross profit of P720,000 on its long-term project which has accumulated costs of P2,880,000. To finish the project, the company estimates that it has to incur additional costs of P1,920,000.
Determine the contract price.
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images
- On March 1, 2019, Elkhart enters into a new contract to build a specialized warehouse for 7 million. The promise to transfer the warehouse is determined to be a performance obligation. The contract states that if the warehouse is usable by November 30, 2019, Elkhart will receive a bonus of 600,000. For every week after November 30 that the warehouse is not usable, the bonus will decrease by 150,000. Elkhart provides the following completion schedule: Required: 1. Assume that Elkhart uses the expected value approach. What amount should Elkhart use for the transaction price? 2. Assume that Elkhart uses the most likely amount approach. What amount should Elkhart use for the transaction price? 3. Next Level What is the purpose of assessing whether a constraint on the variable consideration exists?Batanes Construction Company recognized gross loss of P42,000 on its long-term project which has accumulated costs of P490,000. To finish the project, the company estimates that it must incur additional cost of P735,000. The contract price is:* a. P798,000 b. P1,330,000 c. P1,225,000 d. P1,183,000Excess Construction Corp. has a $16 million contract to construct a building. The company estimates $10.4 million in costs to construct the building and an expected gross profit of $5.6 million. During the current year, the company incurred $3,120,000 of costs on the contract. Under the percentage-of-completion method, how much will Excess Construction Corp. report as revenue in the current year?
- A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the yearwere $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue, cost, and gross profit will the company recognize in the firstand second year of the contract applying the cost recovery method that is required by IFRS?Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,200,000. In the first year of the contract Tullis incurs $3,000,000 of cost and the engineers determined that the remaining costs to complete the project are $5,000,000. Tullis billed $4,000,000 in year 1 and collected $3,200,000 by the end of the end of the year. How should Tullis report Construction in Progress and Billings on Construction in Progress at the end of year 1 on the balance sheet assuming the use of the completed-contract method?At year-end XYZ Company has an in-process construction project with costs totaling $10,000,000. It has billed $8,000,000 on these projects and collected $6,500,000. As it employs the percentage-of-completion method it has also recognized a total of $1,000,000 in profit to date on these contracts. The XYZ balance sheet would report: Selected Answer: Incorrect Asset values totaling $1,500,000 for these projects. Answers: Correct Asset values totaling $4,500,000 for these projects. Asset values totaling $3,500,000 for these projects. Asset values totaling $1,500,000 for these projects. Liabilities values totaling $1,000,000 for these projects.
- The Naples Company uses the percentage-of-completion method and the cost-to-cost method for its long-te construction contracts. On one such contract, Naples expects total revenues of 260,000 and total costs of 200,000. During the first year, Naples incurred costs of 50,000 and billed the customer 30,000 under the contract. At what net amount should Naple's Construction in Progress for this contract be reported at the end of the first year?Shumpert, Inc., entered into a contract that was to take two years to complete, with an estimated cost of $ 1,348,800. The contract price was $1,888,320. Costs of the contract for 2022, the first year, totaled $1,011, 600. If required, round any division to two decimal places and round your final answers to the nearest dollar. a. What was the gross profit reported by the percentage of completion method for 2022? Sfill in the blank 1 b. After the contract was completed at the end of 2023 at a total cost of $1,416, 240, what was the gross profit reported by the percentage of completion method for 2023? Sfill in the blank 2Franklin Construction entered into a fixed-price contract to build a freeway-connecting ramp for $30 million. Construction costs incurred in the first year were $16 million and estimated remaining costs to complete at the end of the year were $17 million. How much gross profit or loss will Franklin recognize in the first year if it recognizes revenue over time according to percentage of completion? What if instead Franklin recognizes revenue upon contract completion?
- Tyro Construction Company has two projects, for which it reported, as of December 31, 20x5, the following information: In thousand pesos: Project A Project B Contract Price P 4,800 860 20x4: Costs incurred P 3,400 Percent completed 75% 20x5: Costs incurred P 1,250 140 Percent Completed 25% 15% Using the percentage-of-completion (over time) method of revenue recognition, gross profit on Project A to be recognized in 20x4 would be: a. P 200,000 ] b. P 300,000Chan Builders Inc entered into a contract with George Company to construct a production plant. At that time, Chan Builders estimated that it would take five years to complete the facility at a total cost of P28,800,000. Chan Builders therefore, pegged the total contract price for the construction of the facility at P34,800,000. During 2010, Chan Builders incurred P7,500,000 in construction costs related to the project. Because of rising material and labor costs, the estimated cost to complete the contract at the end of 2010 amounted to P22,500,000. George was billed and paid 30% on the contract price in accordance with the contract agreement. Compute the Contract Asset (Contract Liability) for 2010. George Co. enters into a contract to build an apartment for Jungle Co. for a fixed fee of ₱20,000,000. At contract inception, George Co. assesses its performance obligations in the contract and concludes that it has a single performance obligation that is satisfied over time. George…The Naples Company uses the overtime/percentage-of-completion method and the point in- time/cost-to-cost method for its long-term construction contracts. On one such contract, Naples expects total revenues of P260,000 and total costs of P200,000. During the first year, Naples incurred costs of P50,000 and billed the customer P30,000 under the contract. At what net amount should Naples' Construction in Progress for this contract be reported at the end of the first year?