Example 9.36. Design a Zeolite-Softener for an industrial concern, using the following data : (i) Qty. of soft water required per hour = 25,000 litres (ii) Hardness present in raw water as CaCO, = 400 ppm. (iii) Hardness to be obtained in the treated supplies = 50 ppm. (iv) Ion exchange capacity of the zeolite = 10 kg of hardness per cu. m. of zeolita (v) Salt required for regeneration of exhausted zeolite = 50 kg per cu. m. of zeolite. Also assume that the industry works for 2 shifts of 8 hours each, per day. Make suitable assumptions where needed, if not given. %3D %3D

Solid Waste Engineering
3rd Edition
ISBN:9781305635203
Author:Worrell, William A.
Publisher:Worrell, William A.
Chapter6: Biological Processes
Section: Chapter Questions
Problem 6.9P: Estimate the production of CO2 and CH4 during the anaerobic decomposition of ethanol. C2H6O.
icon
Related questions
Question

Example 9.36. Design a Zeolite-Softener for an industrial concern, using the
following data :
(i) Qty. of soft water required per hour =
(ii) Hardness present in raw water as CaCO3
(iii) Hardness to be obtained in the treated supplies = 50 ppm.
(iv) Ion exchange capacity of the zeolite = 10 kg of hardness per cu. m. of zeolite
(v) Salt required for regeneration of exhausted zeolite = 50 kg per cu. m. of zeolite.
Also assume that the industry works for 2 shifts of 8 hours each, per day.
Make suitable assumptions where needed, if not given.
25,000 litres
= 400 ppm.
Transcribed Image Text:Example 9.36. Design a Zeolite-Softener for an industrial concern, using the following data : (i) Qty. of soft water required per hour = (ii) Hardness present in raw water as CaCO3 (iii) Hardness to be obtained in the treated supplies = 50 ppm. (iv) Ion exchange capacity of the zeolite = 10 kg of hardness per cu. m. of zeolite (v) Salt required for regeneration of exhausted zeolite = 50 kg per cu. m. of zeolite. Also assume that the industry works for 2 shifts of 8 hours each, per day. Make suitable assumptions where needed, if not given. 25,000 litres = 400 ppm.
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Unit conversion
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Solid Waste Engineering
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,