from the following H.W (2): Draw a project network of the KOLL BUSINESS CENTER information in both AON and AOA methods. complete the forward and backward pass, compute activity slack, and identify the critical path. Use this information to create a Gantt chart for the project. Be sure to show slack for noncritical activities. Hint use the following legend. 1. Legend of AOA KOLL BUSINESS CENTER County Engineers Design Department Activity (ES,EF,FF) Activity ID Description Preceding Activity Activity time Duration(LS,LF,TF) A Application approval None 5 B Construction plans A 15 1. Legend of AON C Traffic study A 10 D Service availability check A 5 ES ID EF E Staff report B,C 15 SL Description F Commission approval B,C,D 10 LS DUR LF G Wait for construction F 170 EF H Occupancy E,G 35

Computer Networking: A Top-Down Approach (7th Edition)
7th Edition
ISBN:9780133594140
Author:James Kurose, Keith Ross
Publisher:James Kurose, Keith Ross
Chapter1: Computer Networks And The Internet
Section: Chapter Questions
Problem R1RQ: What is the difference between a host and an end system? List several different types of end...
icon
Related questions
Question
from the following
H.W (2): Draw a project network of the KOLL BUSINESS CENTER
information in both AON and AOA methods. complete the forward and backward pass,
compute activity slack, and identify the critical path. Use this information to create a Gantt
chart for the project. Be sure to show slack for noncritical activities. Hint use the following
legend.
1. Legend of AOA
KOLL BUSINESS CENTER County
Engineers Design Department
Activity (ES,EF,FF)
Activity ID
Description
Preceding
Activity
Activity
time
Duration(LS,LF,TF)
A
Application approval
None
5
B
Construction plans
A
15
1. Legend of AON
C
Traffic study
A
10
D
Service availability check
A
5
ES
ID
EF
E
Staff report
B,C
15
SL
Description
F
Commission approval
B,C,D
10
LS
DUR LF
G
Wait for construction
F
170
EF
H
Occupancy
E,G
35
Transcribed Image Text:from the following H.W (2): Draw a project network of the KOLL BUSINESS CENTER information in both AON and AOA methods. complete the forward and backward pass, compute activity slack, and identify the critical path. Use this information to create a Gantt chart for the project. Be sure to show slack for noncritical activities. Hint use the following legend. 1. Legend of AOA KOLL BUSINESS CENTER County Engineers Design Department Activity (ES,EF,FF) Activity ID Description Preceding Activity Activity time Duration(LS,LF,TF) A Application approval None 5 B Construction plans A 15 1. Legend of AON C Traffic study A 10 D Service availability check A 5 ES ID EF E Staff report B,C 15 SL Description F Commission approval B,C,D 10 LS DUR LF G Wait for construction F 170 EF H Occupancy E,G 35
Expert Solution
steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Recommended textbooks for you
Computer Networking: A Top-Down Approach (7th Edi…
Computer Networking: A Top-Down Approach (7th Edi…
Computer Engineering
ISBN:
9780133594140
Author:
James Kurose, Keith Ross
Publisher:
PEARSON
Computer Organization and Design MIPS Edition, Fi…
Computer Organization and Design MIPS Edition, Fi…
Computer Engineering
ISBN:
9780124077263
Author:
David A. Patterson, John L. Hennessy
Publisher:
Elsevier Science
Network+ Guide to Networks (MindTap Course List)
Network+ Guide to Networks (MindTap Course List)
Computer Engineering
ISBN:
9781337569330
Author:
Jill West, Tamara Dean, Jean Andrews
Publisher:
Cengage Learning
Concepts of Database Management
Concepts of Database Management
Computer Engineering
ISBN:
9781337093422
Author:
Joy L. Starks, Philip J. Pratt, Mary Z. Last
Publisher:
Cengage Learning
Prelude to Programming
Prelude to Programming
Computer Engineering
ISBN:
9780133750423
Author:
VENIT, Stewart
Publisher:
Pearson Education
Sc Business Data Communications and Networking, T…
Sc Business Data Communications and Networking, T…
Computer Engineering
ISBN:
9781119368830
Author:
FITZGERALD
Publisher:
WILEY