Given the early occurrence time and late occurrence time of the starting event is 10 and 12 days respectively, and early occurrence time and late occurrence time of finishing even of the same activity is 22 and 26 days respectively with 10 times unit of estimated duration of the project what is the total float?

Solid Waste Engineering
3rd Edition
ISBN:9781305635203
Author:Worrell, William A.
Publisher:Worrell, William A.
Chapter3: Collection
Section: Chapter Questions
Problem 3.16P
icon
Related questions
Question

Given the early occurrence time and late occurrence time of the starting event is 10 and 12 days respectively, and early occurrence time and late occurrence time of finishing even of the same activity is 22 and 26 days respectively with 10 times unit of estimated duration of the project what is the total float?

Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Solid Waste Engineering
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning