Hardhat Construction Company has a contract to construct a $4,500,000 bridge at an estimated cost of $4,000,000. The contractis to start in July 2014, and the bridge is to be completed in October 2016. The following data pertain to the construction period. 2014 2015 2016 Costs to date $1,000,000 3,000,000 900,000 $2,916,000 1,134,000 2,400,000 1,750,000 $4,050,000 Estimated costs to complete Progress billings during the year Cash collected during the year 1,200,000 2,000,000 750,000 Record the journal entries for 2014, 2015, and 2016 using the percentage of completion method Record the income statement and balance sheet for 2014, 2015, and 2016
Q: Puff and Stuff Construction began a construction project in 2016. The contract price was…
A: Percentage of completion = Cumulative cost incurred at end of year / Total estimated cost Revenue…
Q: MD Construction entered into a contract beginning January 1, 2010 to build a parking complex. It has…
A: Percentage-of-completion method can be referred to as the method of accounting costs in case of long…
Q: The Rushing Construction Company obtained a construction contract to build a highway and bridge over…
A: The percentage of completion method - It is an accounting method in which expenses and revenue of…
Q: On February 1, 2014, Marsh Contractors agreed to construct a building at a contract price of…
A:
Q: MD Construction entered into a contract beginning January 1, 2010 to build a parking complex. It has…
A:
Q: M6-16 Using Percentage-of-Completion and Completed Contract Methods Halsey Building Company signed a…
A: a.Calculate the gross profit under percentage of completion method as follows:
Q: Maya Co. which is a publicly traded company started to build a 30-story Condo building in May 2018.…
A:
Q: In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Requirement 4 : 2018 2019 2020 Revenue $ 2,800,000 $ 3,692,964 $…
Q: M6-16 Using Percentage-of-Completion and Completed Contract Methods Halsey Building Company signed a…
A: We’ll answer the first question since the exact one wasn’t specified. Please submit a new question…
Q: In 2016, Omega Construction began work on a contract with a price of $850,000 and estimated costs of…
A: Introduction:- Gross profit is the profit a company generates after subtracting the expenses of…
Q: Ahmed construction began work on a $10,000,000 contracts in 2016 to construct a bridge. During 2016,…
A: COST RECOVERY METHOD Contract price $10,000,000 Cost incurred during Current year (2016)…
Q: National Construction agreed to construct a building for Berninger Corp with construction beginning…
A: Solution: Under percentage of completion method of long term construction contracts, revenue is…
Q: Ahmed construction began work on a OMR 10,000,000 contracts in 2016 to construct a bridge. During…
A: Information given in question Contract price 10,000,000 Cost incurred during the year…
Q: On March 1, 2022, AGGREGATES Company enters a contract to build a hotel which is estimated to cost…
A: We first need to understand the concept of revenue recognized over a period of time. When goods or…
Q: Tamarisk Industries Inc. started construction of a manufacturing facility for its own use at an…
A: Depreciation refers to that amount of monetary value of an assets which decreases overtime due to…
Q: On July 1, 2020, Oliver Construction Corp. contracted to build an office building for Annalise Inc.,…
A: Percentage Completion Method: The percentage of completion may be calculated by dividing current…
Q: BUILDERS Construction is constructing an office building under contract. contract calls for progress…
A: The construction contract seems to be a consensual or contractually enforceable contract between two…
Q: Triple Take Construction Co. began construction of a project in 2017 for a contract price of…
A: The question is based on the concept of Accounting Standard on Construction contracts.
Q: Sunland Construction Company has entered into a non-cancellable contract beginning January 1, 2020,…
A: Percentage of completion method: The percentage of completion method is a revenue recognition…
Q: In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: 2018 2019 2020 Revenue 3000000 3500000 35000000 Gross profit (loss) 360000 1200000 574000
Q: SMDC Construction signed a contract to build a building over a period 3 years for a price of…
A: Percentage of Completion = Cost Incurred during a year / Total Estimated Cost ×100 Construction…
Q: DM, Inc. works on a P10,500,000 contract in 2015 to construct an office building. During 2015, DM,…
A: Introduction: Whenever a company employs the installments sales strategy to record its sales…
Q: On July 1, 2017, Cusak Construction Company Inc. contracted to build an office building for Candy…
A: Under Percentage completion method, the revenues recognised is equal to percentage of work completed…
Q: Dalton Construction Co. contracted to build a bridge for $10,000,000. Construction began in 2021 and…
A: “Since you have posted a question with multiple sub-parts, we will solve first three subparts for…
Q: Tamarisk Industries Inc. started construction of a manufacturing facility for its own use at an…
A: Weighted average interest rate on General borrowings =10%×$1,350,000…
Q: PAPASA Co. has consistently used the percentage of completion to account for its construction…
A: Total cost = Cost incurred to date + Estimated cost to complete = 2,700,000 + 900,000 = P3,600,000
Q: On January 2, 2017, Indian River Groves began construction of a new cilr ocessi 48. automated plant…
A: Interest represents the specific amount required to be paid over a period of time for the amount…
Q: February 1, 2021, Arrow Construction Company entered into a three-year construction.contract to…
A: "Since you have asked multiple sub part question we will solve the first three sub part question for…
Q: Hardhat Construction Company has a contract to construct a €4,500,000 bridge at an estimated cost of…
A: As per percentage completion method, the profit and loss is recognized based on percentage of work…
Q: At the beginning of 2009, Florida Road Construction entered into a contract to build a road for the…
A: Revenue Recognition: Revenue recognition is the recording of revenues in the books of the company…
Q: Triple Take Construction Co, began construction of a project in 2017 for a contract price of…
A: The revenue, cost, and profit are to be recorded based on % of completion. % completion = (Cost…
Q: in 2021, the southgate construction company entered into a contract to construct a bridge for…
A: The following calculations are done as per the information provided by the South gate construction…
Q: 24 On January 1, 2016, AVIDA was contracted to construct a townhouse for SM Corp. for a total…
A: The contract revenue can be recognized on the basis of percentage of the total cost incurred during…
Q: A. Compute the avoidable interest on this project. (Use interest rates rounded to 2 decimal places,…
A:
Q: On July 1, 2016, ABC Construction Corp. contracted to build an office building for XYZ, Inc. for a…
A: A long-term contract for construction workers is a contract that details a period lasting longer…
Q: Skysong Industries Inc. started construction of a manufacturing facility for its own use at an…
A: Weighted-average accumulated expenditures $7,480,000 Construction Loan…
Q: Archer Construction Company began work on a $420,000 construction contract in 2017. During 2017,…
A: a.
Q: Shanahan Construction Company has entered into a contract beginning January 1, 2020, to build a…
A: Percentage of completion and complete contract method are used to recognize revenue. Under…
Q: Triple Take Construction Co. began construction of a project in 2017 for a contract price of…
A: The construction contracts are long-term contracts that means it is completely performed in…
Q: At the beginning of 2009, Florida Road Construction entered into a contract to build a road for the…
A: Revenue Recognition: Revenue recognition is the recording of revenues in the books of the company…
Q: On March 1, 2022, ABC Co. was contracted to construct a building for a customer at a total contract…
A: Solution: Under percentage of completion method, revenue is recognized based on % work completed…
Q: On March 1, 2020, Pechstein Construction Company contracted to construct a factory building for…
A:
Q: REQUIRED: a) Using percentage-of-completion method, prepare schedules to compute the profit and…
A: The amount earned from the business operation is known as operating income, but when the expenses to…
Q: At the beginning of 2009, Florida Road Construction entered into a contract to build a road for the…
A: Revenue Recognition: Revenue recognition is the recording of revenues in the books of the company…
Q: American Construction Company has entered into a contract with American University in Cairo…
A: Journal entry: It is the duty of the accountant to record and summarize business economic and non…
Q: Teal Mountain Industries Inc. started construction of a manufacturing facility for its own use at an…
A:
Q: On January 1, 2017, SJT Corp. made an initial investment of $1,000,000 and construction began on a…
A: Borrowing Costs: It is the cost incurred in connection with borrowing of funds for construction…
Q: In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: A balance sheet is a financial statement that presents a company's assets, liabilities and…
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 7 images
- ABC Construction Company began work on a contract in 2022 and completed the contract in 2023. The total contact price was P8,500,000. Information related to the construction project are as follows: 2022 2023 Costs incurred during the year P1,200,000 P6,250,000 Estimated costs to complete 4,800,000 - Progress billings during the year 1,450,000 7,050,000 Collections during the year 800,000 6,000,000 How much is the gross profit to be recognized in 2023?in 2021, the southgate construction company entered into a contract to construct a bridge for $12,000,000. the bridge was completed in 2023. information related to the contract is as follows: 2021 2022 2023 cost incurred during the year $1,840,000 $3,760,000 $4,500,000 estimated costs to complete as of year-end $6,160,000 $4,400,000 $0 billings during the year $3,000,000 $4,000,000 $5,000,000 cash collections during thee year $2,600,000 $3,900,000 $5,100,000 southgate recognizes revenue using the completed contract method. what amount will southgate show on the balance sheet at december 31, 2022? multiple choice costs in excess of billings (asset) $5,600,000 billings in excess of costs (liability) $1,400,000 billings in excess of costs (liability) $280,000 costs in excess of billings (asset) $280,000 If answered within one hour,it would be appreciable!! answer all questions.On March 1, 2022, AGGREGATES Company enters a contract to build a hotel which is estimated to cost P31,200,000. The company recognizes construction revenue over time. Data on this project for 2022-2024 follow: Contract Billings Costs incurred Est'd Costs to complete 2022 10,500,000 5,460,000 20,540,000 2023 12,500,000 9,984,000 13,156,000 2024 14,440,000 15,756,000 - The contract contains a penalty clause that penalizes the company a reduction of P70,000 from the contract price for every week of delay. In 2024, the contract was delayed for 8 weeks. What is the gross profit for 2024?A. 1,164,000 C. 1,724,000B. 1,466,400 D. 1,824,000
- Ava Limited., which has a calendar year end, has entered into a non-cancellable fixed-price contract for $2.8 million beginning September 1, 2015, to build a road for a municipality. It has been estimated that the road construction will be complete by June 2017. The following data pertain to the construction period. 2015 2016 2017 Costs to date $867,000 $1,804,800 $2,346,000 Estimated costs to complete 1,683,000 1,015,200 0 Progress billings to date (non-refundable) 921,000 2,296,000 2,800,000 Cash collected to date 767,000 2,177,000 2,800,000 Using the percentage-of-completion method, calculate the percentage complete for 2015 and 2016. (Round answers to 2 decimal places, e.g. 61.75%.)On March 1, 2022, ABC Co. was contracted to construct a building for a customer at a total contract price of P16,500,000. The building was estimated to be completed in 2024. The following data were made available: 2022 2023 2024 Contract costs incurred P6,400,000 P5,200,000 P2,900,000 Estimated costs to complete 6,400,000 2,900,000 - Progress billings each year 6,400,000 7,000,000 3,100,000 How much is the realized gross profit for 2023?Assume that Sunland Construction Company has a non-cancellable contract to construct a $4,520,000 bridge at an estimated cost of $4,068,000. The contract is to start in July 2023, and the bridge is to be completed in October 2025. The following data pertain to the construction period. Assume that progress billings are non-refundable. 2023 2024 2025 Costs to date (12/31) $1,017,000 $2,928,960 $4,576,500 Estimated costs to complete (12/31) 3,051,000 1,647,540 0 Progress billings during the year 968,000 2,418,000 1,134,000 Cash collected during the year 817,000 1,897,000 1,806,000 The revised estimates for the bridge contract are as follows. 2023 Original Estimates 2024 Revised Estimates Contract price $4,520,000 $4,520,000 Estimated total cost 4,068,000 4,576,500* Estimated gross profit $452,000 Estimated loss $(56,500) *$2,928,960 + $1,647,540 (a1) Under the percentage-of-completion method, calculate…
- In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,184,000 $ 3,510,000 $ 2,316,600 Estimated costs to complete as of year-end 5,616,000 2,106,000 0 Billings during the year 2,120,000 3,574,000 4,306,000 Cash collections during the year 1,860,000 3,400,000 4,740,000 Westgate recognizes revenue over time according to percentage of completion. rev: Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.) 2018 2019 2020 Cost incurred during the year $ 2,184,000 $ 3,860,000 $ 3,260,000 Estimated costs to complete as…1.On March 1, 2022, AGGREGATES Company enters a contract to build a hotel which is estimated to cost P31,200,000. The company recognizes construction revenue over time. Data on this project for 2022-2024 follow:Contract BillingsCosts incurredEst’d Costs to Complete2022 10,500,000 5,460,000 20,540,0002023 12,500,000 9,984,000 13,156,0002024 14,440,000 15,756,000 -The contract contains a penalty clause that penalizes the company a reduction of P70,000 from the contract price for every week of delay. In 2024, the contract was delayed for 8 weeksWhat is the gross profit for 2024?A. 1,164,000 C. 1,724,000B. 1,466,400 D. 1,824,000 2.MOC Construction Company started work on three job sites during the current year. Any costs incurred are expected to be recoverable. Data relating to the three jobs are given below:Site Contract PriceCost IncurredEstimated Costs to CompleteBillings on ContractCollections on Billings1 5,000,000 3,750,000 - 5,000,000 5,000,0002 7,000,000 1,000,000 4,000,000 900,000…DM, Inc. works on a P10,500,000 contract in 2015 to construct an office building. During 2015, DM, Inc. uses thecost to cost method. At December 31, 2015, the balances in certain accounts were: Construction in Progress – P3,780,000;Accounts Receivable – P360,000; and Billings on Construction in process – P1,800,000; contract retention – P180,000;Mobilization fee – P140,000. At December 31, 2015, the estimated cost at completion is P7,350,000. Determine the realizedgross profit in 2015
- In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara Countyfor $10,000,000. The road was completed in 2020. Information related to the contract is as follows:2018 2019 2020Cost incurred during the year $2,400,000 $3,600,000 $2,200,000Estimated costs to complete as of year-end 5,600,000 2,000,000 –0–Billings during the year 2,000,000 4,000,000 4,000,000Cash collections during the year 1,800,000 3,600,000 4,600,000Westgate recognizes revenue over time according to percentage of completion.Required:1. Calculate the amount of revenue and gross profit to be recognized in each of the three years.2. Prepare all necessary journal entries for each of the years (credit “various accounts” for construction costsincurred).3. Prepare a partial balance sheet for 2018 and 2019 showing any items related to the contract. Indicate whetherany of the amounts shown are contract assets or contract liabilities.4. Calculate the amount of revenue and gross…On July 1, 2016, ABC Construction Corp. contracted to build an office building for XYZ, Inc. fora total price of P975,000. 2016 2017 2018Contract cost incurred to date 75,000 600,000 1,050,000Estimated costs to complete the contract 675,000 400,000 -Billings to XYZ, Inc. 150,000 550,000 275,0001. Under the percentage of completion method, how much is the Construction-in-Progressat December 31,2017?2. Under the zero-profit method, how much is the Construction-in-Progress, net of ProgressBillings at December 31, 2017?3. Under the percentage of completion method, how much is the realized gross profit/ (loss)at December 31, 2018?On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2018, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2019, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2019 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2020 after additional costs of $3,800,000 were incurred. The company’s fiscal year-end is December 31. This project does not qualify for revenue recognition over time. Required:1. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2018.2. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2019.