i) There is the need to rerun a survey on the existing coordinates. It is important to compare the z-coordinate of the first vertical control found underground at the topmost level in the shaft with an existing value what is the challenge of accomplishing this task?              (ii)  What constitutes a good reconnaissance for the road survey?

Traffic and Highway Engineering
5th Edition
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Garber, Nicholas J.
Chapter14: Highway Surveys And Location
Section: Chapter Questions
Problem 5P
icon
Related questions
Question

(i) There is the need to rerun a survey on the existing coordinates. It is

important to compare the z-coordinate of the first vertical control found

underground at the topmost level in the shaft with an existing value what is the challenge of accomplishing this task?           

  (ii)  What constitutes a good reconnaissance for the road survey?

Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Construction surveys
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning