If Task B is delayed by 2 days, which of the following task will be directly impacted? Task Duration Predecessor A 3 days - B 5 days A C 4 days B D 2 days B E 1 day C, D F 1 day E a. Task F b. Task C c. None of the above. d. Task E e. Task D
Q: Describe the effective inventory management process of medicines in a hospital? Please answer at…
A: An effective inventory management process for medicines in hospital involves several steps. First,…
Q: What is risk management approach?
A: Effective risk management is an indispensable element of operations management. It entails the…
Q: Case Study 2: Quality Management Your line manager has become increasingly concerned about the…
A: *As per guidline first three parts are answerable please repost the remaining parts. Mean x =…
Q: In the operations section of your business strategy, you should describe any problems with…
A: The operations segment is an integral part of any business plan, and it describes the regular…
Q: How can the principles of lean manufacturing be applied to a production plant to improve efficiency,…
A: Lean manufacturing is a production philosophy that emphasises reducing waste, boosting…
Q: Product design engineer: individual has the ultimate responsibility for the development of the…
A: Product development is the process of creating as well as designing a new offering for the market.…
Q: Do you think the actions of the board of directors were enough to uphold Papa John’s reputation
A: Papa John's is a prominent American pizza restaurant business whose creator, John Schnatter, has…
Q: Case 1: Western Chassis produces high-quality polished steel and aluminum sheeting and two lines of…
A: Suppose-A Pounds of Steel Sheeting to be polishedB Pounds of Aluminium Sheeting to be polishedC No.…
Q: Your organisation has made the decision to duplicate its product database across numerous servers in…
A: Operations management is essential to efficiently operating an organization's systems and…
Q: Now that we have been using CAPSIM, let’s look back at your experiences in your practice work. How…
A: Decision-making is the process of taking a decision that helps the business in achieving its target.…
Q: Reverse engineering or product decomposition is a method to understand how a product works and it…
A: Reverse engineering is the technique of deconstructing or disassembling an item to comprehend how it…
Q: Facility Location. A paper products manufacturer has enough capital to build and manage some…
A: Find the Given details below: Given details: Plant site Cities Los Angeles Topeka New…
Q: Find the value of X in the following Flow Shop data consisting of 5 jobs which are to be processed…
A:
Q: Why should an organisation make an effort to successfully integrate its external suppliers?
A: A supplier in a supply chain is a person who provide the goods and services to the next entity with…
Q: Plan out how complaints will be recorded and tracked using an activity diagram.
A: Customer satisfaction and organisational performance are both dependent on effective complaint…
Q: Suppose that Baldwin will increase its automation to 6.5 this year. Each new unit of automation…
A: The cost of investment refers to the total expenses incurred by a company or individual when making…
Q: 4. Consider the following table indicating the number of units of clothing and food produced per…
A: Ans) Country T produce more clothing and food as compared to country J. Thus, Country T has…
Q: Operation management The following set of six jobs is to be processed through two work centers at…
A: answer) (1). The table below shows the given data. Job Printing (hrs) binding(hrs) A 10 5 B…
Q: College Creations, Inc (CC), builds a loft that is easily adaptable to most dorm rooms or apartments…
A: Selling price = $500Variable (Production) cost = $300 per loftFixed costs = $100,000
Q: The normal time for this operation = enter your response here minutes (round your response to…
A: Here, each observation number is given with the time data, I would determine the average time for…
Q: Operation mangement An online shoe retailer's annual cost of holding inventory is 30 percent.…
A: Inventory controlling is the process of controlling those activities in the business that increases…
Q: Final quality of a product is determined by both “Quality of Design” and Quality of Conformance,…
A: Ans a) In the field of manufacturing, it is commonly known that the final quality of a product is…
Q: Why is it essential to include an exception into the timetable of a process
A: Process management is crucial for organisations to fulfil their goals and remain competitive in…
Q: f you could create a dashboard from scratch for your business, what metrics would you track
A: Here, the dashboard would be prepared from scratch for a specific business, A business dashboard is…
Q: O Suppose we wish to set up a production plan for the JC Company for the next six months. We are…
A: EOQ or economic order quantity is a business production model that lets an organization know how…
Q: QUESTION 15 The Sweet Success Bakery sells 800 cakes at a price of $20 per cake. Its total economic…
A: It is the total cost of producing a good or service, including both explicit costs and implicit…
Q: What are the most important benefits of managing projects? What would it be like without project…
A: Here, for this Q, first, I would discuss the most important benefits of managing projects, and what…
Q: The manager of Arbor, Incorporated, is considering raising its current price of $50 per unit by 10%.…
A: Cost is the amount that is incurred by a company while producing goods and services to deliver the…
Q: A large insurance company maintains a central computing system that contains a variety of…
A: Find the Given details below: Given details: Arrival time λ 38 Calls per hour Service time μ…
Q: How can you set an effective content distribution goal? O Craft a SMART goal and confirm this aligns…
A: When you publish, share, and promote content in various formats and through various channels, you…
Q: 3.A bottle of wine costs the operation $11.00 and yields four glasses. What is the cost perglass?
A: "Costs the operation" signifies the amount spent by an entity to produce a good or service. It is…
Q: Any company's main purpose is to benefit stakeholders and competitors. d. service 4. In a…
A: The supply chain is a vital value chain in a manufacturing organisation that oversees the movement…
Q: Develop a strategy map of a Medical Home using the attached template.
A: The strategy map is the visual representation of the business's overall strategy that gives quick…
Q: How important is it to address management-employee conflicts in the operations section of your…
A: Disagreements about how tasks are carried out will inevitably come up at some time when a team of…
Q: The goal of utilitarian ethics is to establish rules for why certain behaviors are ethical. b. do…
A: Business ethics are the rules, principles, and policies that are followed by every member of the…
Q: CVS chain prefers to operate one outlet in a town that has four major market segments. The number of…
A:
Q: Explain how the organization’s strategic plan should incorporate those CSFs into goals for the…
A: Critical Success Factors (CSFs) are key areas that organisation must focus on to achieve its…
Q: How much total time is required to process all the seven jobs? Illustrate this using a Gant Chart.
A: Sequencing is an appropriate order of plan as per which the process of operations works. It defines…
Q: What are some of the advantages that come along with using a strategy that operates in stages?
A: A staged approach in operations management is a way to accomplish organizational goals by segmenting…
Q: Is it true that lean management tends to disregard certain organisational effectiveness factors?…
A: Lean Management's commitment to instilling continuous improvement, which ensures that every person…
Q: Manning Systems is a commercial software vendor that sells billing and other financial software to…
A: Answer) (a) We will use the following steps to determine the allocation to each of the divisions…
Q: How are supply networks for organisations that provide services different from supply chains for…
A: A successful business relies on happy customers. Supply chain management's core purpose is to track…
Q: "Data and analytics are integral for any business decision". Critically evaluate this statement with…
A: In the digital age, data and analytics have become integral to businesses in making informed…
Q: with the use of relevant exampleds, discuss the impact of tactical planning on successful logistics…
A: Here, I would first discuss tactical planning, then, I would discuss the impact of tactical planning…
Q: Construct a PERT network from the following table. Find the critical path and variance for ea event,…
A: A network diagram shows the link of each task with the duration taken by each activity with respect…
Q: Why do systems developers need ISO?
A: The International Standards Organisation is a non-governmental organisation that creates and…
Q: Draw the activity on node diagram and determine the ES, EF, LS, LF. Determine the critical path and…
A: A network diagram shows the link of each task with the duration taken by each activity with respect…
Q: Provide an illustration of one of the four access control strategies. How is this option…
A: Having the ability to limit or permit access to certain locations or resources is crucial to the…
Q: What does product quality mean for Amazon? What functional-level strategies has Amazon pursued to…
A: The degree to which a good or service satisfies the requirements, demands, and requirements of the…
Q: QUESTION THREE Given the LP below: a) Solve the problem using big M-method Minimize Z = 3X1 +4X2 s.t…
A: MIN Z = 3x1 + 4x2Subject to -4x1 + x2 ≥ 30-x1 - 4x2 ≤ -184x1 + 3x2 ≥ 28x1, x2 ≥ 0
If Task B is delayed by 2 days, which of the following task will be directly impacted?
Task | Duration | Predecessor |
---|---|---|
A | 3 days | - |
B | 5 days | A |
C | 4 days | B |
D | 2 days | B |
E | 1 day | C, D |
F | 1 day | E |
a.
Task F
b.
Task C
c.
None of the above.
d.
Task E
e.
Task D
Step by step
Solved in 3 steps with 1 images
- A bar chart shows the number and type of resources you need throughoutyour project is called a _______________.A. Organizational ChartB. Resource histogramC. Resource ScheduleD. Staffing Timetable You have identified an opportunity to potentially increase the project’s value.Which of the following is an example of enhancing that opportunity?A. By taking additional actions, you increase the potential reward without reducing itsprobabilityB. By forming a partnership with another company, the project’s value will increase forboth companiesC. By taking out insurance, you can reduce potential costs to the projectD. By documenting the opportunity in the register, you can keep track of it and ensureit gets exploited(1) Suppose a project manager is reviewing the project management plan, the work performance data, and the project schedule. She is getting ready to do next? Work the project plan. Plan the project schedule. Start Control Schedule. Create the WBS. (2) During the Control Schedule process, what is one of the most common outputs? Stakeholder meeting Team meeting Vacation request Change requestManagement Firm is a consulting company that specializes in the development of decision support systems. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Report generation 2 8 12 B Web scraping 4 9 11 C Testing A, B 1 1 1 (b) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.)
- when discussing processes related to Project Execution, the ISO 10006 stabdard splits this category into different project groups. Which of the following is not one of these subcategories? a. Human resource-related processes b. Procurement processes c. Time related processes d. risk-related processConsider a project to produce custom door moldingsfor GMC Acadia cross-over vehicles, described inTable 7.4. a. If you start the project immediately, when will it be finished?b. You are interested in completing your project as soon aspossible. You have only one option. Suppose you couldassign Employee A, currently assigned to activity G, tohelp Employee B, currently assigned to activity F. Eachweek that Employee A helps Employee B will result inactivity G increasing its time by one week and activity Freducing its time by one week. How many weeks shouldEmployee A work on activity F?Executing processes exclude coordinating people and other resources to carry out the various plans and create the products, services, or results of the project or phase Select one: True False A ______ is a series of actions directed toward a particular result. Select one: a. project b. process c. plan d. goal A dependency or relationship pertains to the sequencing of project activities or tasks Select one: True False Determine budget output Select one: a. Work performance information, cost forecasts, change requests, project management plan updates, project documents updates, organizational process assets updates b. Activity cost estimates, basis of estimates, project documents updates c. Cost management plan d. Cost baseline, project funding requirements, project documents updates
- You are in charge of a project at the local community center. The center needs to remodel one ofthe rooms in time for the start of a new program. Delays in the project mean that the center mustrent other space at a nearby church at additional cost. Time and cost data for your project arecontained in below table. Your interest is in minimizing the cost of the project to the communitycenter.Using the normal times for each activity, what is the earliest date you can complete the project?Suppose the variable overhead costs are $50 per day for your project. Also, suppose that thecenter must pay $40 per day for a temporary room on day 15 or beyond. Find the minimum-costproject schedule using below format.The AON diagram for the community center project is below. Crash 4 times and find total cost.A recent IBM study of 585 mobile app developers and managers found that only one-third of mobile development projects were on schedule, within budget, and achieved their objectives. What dangers exist for businesses like FIMC that create and release mobile apps so quickly?Management Firm is a consulting company that specializes in the development of decision support systems. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Report generation 2 8 12 B Web scraping 4 9 11 C Testing A, B 1 1 1 (A) Based solely on the critical path, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.) (b) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.)
- Which of the following statements is correct with respect to slack time?a. The slack time of an activity is the latest completion time of the activity minus theearliest completion time.b. The slack time of an activity is the latest start time of the activity minus the earliest start time.c. The slack time of an activity determines how long an activity can be delayed withoutimpacting the overall completion of the project.d. All of these statements are correct.Freed works for a traditional company that expects him to start at 8.30 a.m. and leave at 5.30 p.m. or later every day. Most of his work is done on a project basis and, as a manager, he is responsible for the quality of work that is produced and for meeting deadlines, as the nature of his work involves meeting deadlines, achieving certain objectives, and hitting targets. On most days of the week, there is often extra work to be done on a project, and Freed stays late in the office or brings his work home. Occasionally, his director and colleagues find him missing important information in a meeting because he was thinking about something else.People sometimes think about something other than what they’re doing. Their minds wander, whether they are trying to read important emails, speaking to clients, updating the sales figures, or talking to colleagues, creating barriers in communication not only for themselves but also their receivers. Justify this statement in keeping with the…All projects utilise several different resources to successfully complete the project successfully tothe customer or sponsors requirements.Resources add another dimension to planning and scheduling. This includes people, materials,equipment, tool, facilities and so forth.The quantity and availability of these resources are often limited and cause project to face risks orconstraints which needs to be managed carefully.With the above statements , differentiate between Resource smoothing and resourcelimited scheduling then to substantiate your answer by providing at least two (2) situations whereresource limited scheduling may occur