In a CPM network, the critical path has five activities. Their durations are tabulated next. Duration Activity Optimistic (To) Most Likely (Tm) Pessimistic (Tp) A 2 5 9 B 3 4 8 C 4 6 9 D 5 10 20 E 3 5 9 Compute the following: The probability that the project will finish by the end of day 32 The probability that the project will finish by the end of day 34 The probability that the project will finish before day 30
In a CPM network, the critical path has five activities. Their durations are tabulated next. Duration Activity Optimistic (To) Most Likely (Tm) Pessimistic (Tp) A 2 5 9 B 3 4 8 C 4 6 9 D 5 10 20 E 3 5 9 Compute the following: The probability that the project will finish by the end of day 32 The probability that the project will finish by the end of day 34 The probability that the project will finish before day 30
Residential Construction Academy: House Wiring (MindTap Course List)
4th Edition
ISBN:9781285852225
Author:Gregory W Fletcher
Publisher:Gregory W Fletcher
Chapter7: Introduction To Residential Service Entrances
Section: Chapter Questions
Problem 6RQ
Related questions
Question
- In a CPM network, the critical path has five activities. Their durations are
tabulated next.
Duration |
|||
Activity |
Optimistic (To) |
Most Likely (Tm) |
Pessimistic (Tp) |
A |
2 |
5 |
9 |
B |
3 |
4 |
8 |
C |
4 |
6 |
9 |
D |
5 |
10 |
20 |
E |
3 |
5 |
9 |
Compute the following:
- The probability that the project will finish by the end of day 32
- The probability that the project will finish by the end of day 34
- The probability that the project will finish before day 30
- The probability that the project will finish on day 32
- The probability that the project will finish no later than day35
- The probability that the project will finish at least 2 days early
- The probability that the project will finish at least 2 days late
- The probability that the project will finish on day 32 ±1 day
- The completion date with at least a 90% confidence level
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 5 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Residential Construction Academy: House Wiring (M…
Civil Engineering
ISBN:
9781285852225
Author:
Gregory W Fletcher
Publisher:
Cengage Learning
Residential Construction Academy: House Wiring (M…
Civil Engineering
ISBN:
9781285852225
Author:
Gregory W Fletcher
Publisher:
Cengage Learning