In the welding operations of a bicycle manufacturer, a bike frame has a flow time of about 12.75 hours. The time in the welding operation is spent as follows: 2 hours waiting in front of the cutting machine for the batch to start, 2 hours waiting for the setup of the machine, 2 hour waiting for the other pieces of the batch to go through cutting, 1 minute at the cutting machine, and 2 hours waiting for the transfer to the welding machine. Then, at the welding machine, the unit spends 1 hour waiting in front of the welding machine for the batch to start, 1 hour waiting for the setup of the welding machine, 0.75 hour waiting for the other pieces of the batch to go through welding, 0.25 minute at the welding machine, and 2 hour waiting for the transfer to the next department. (Round your percentage answer to 4 decimal places.) Determine the exact flow time. What is the value-added percentage of the flow time? 0.0604 percent

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question
In the welding operations of a bicycle manufacturer, a bike frame has a flow time of about 12.75 hours. The time in the welding
operation is spent as follows: 2 hours waiting in front of the cutting machine for the batch to start, 2 hours waiting for the setup of the
machine, 2 hour waiting for the other pieces of the batch to go through cutting, 1 minute at the cutting machine, and 2 hours waiting for
the transfer to the welding machine. Then, at the welding machine, the unit spends 1 hour waiting in front of the welding machine for
the batch to start, 1 hour waiting for the setup of the welding machine, 0.75 hour waiting for the other pieces of the batch to go through
welding, 0.25 minute at the welding machine, and 2 hour waiting for the transfer to the next department.
(Round your percentage answer to 4 decimal places.)
Determine the exact flow time. What is the value-added percentage of the
flow time?
0.0604 percent
Transcribed Image Text:In the welding operations of a bicycle manufacturer, a bike frame has a flow time of about 12.75 hours. The time in the welding operation is spent as follows: 2 hours waiting in front of the cutting machine for the batch to start, 2 hours waiting for the setup of the machine, 2 hour waiting for the other pieces of the batch to go through cutting, 1 minute at the cutting machine, and 2 hours waiting for the transfer to the welding machine. Then, at the welding machine, the unit spends 1 hour waiting in front of the welding machine for the batch to start, 1 hour waiting for the setup of the welding machine, 0.75 hour waiting for the other pieces of the batch to go through welding, 0.25 minute at the welding machine, and 2 hour waiting for the transfer to the next department. (Round your percentage answer to 4 decimal places.) Determine the exact flow time. What is the value-added percentage of the flow time? 0.0604 percent
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,