On Week a) Smell Fresh hand 1 2 Forecast 20 20 PAB Customer Orders Available to Promise 5 3 20 50 30 3222 4 5 6 7 8 Problem 6: Georgia Clay and Gravel was updating the MPS record for one of its products, Smell Fresh Cat Litter. Partially-completed MPS time-phased record is given below. 20 30 30 30 30 30 Week 10 30 50 20 40 10 Item: Smell Fresh On hand 1 2 3 4 5 6 7 8 MPS MPS lot size=50 50 50 50 50 g| Forecast 20 20 Orders 5 20 50 233 220 20 20 30 30 30 30 30 On Week b) Smell Fresh hand 2 3 4 5 6 7 8 9 Forecast Customer Orders PAB Available to Promise MPS MPS lot size=50 45 Projected available balance Available-to-promise MPS MPS Lot Size = 50. 50 10 30 50 50 50 a) Complete the MPS time-phased record (the first table on the left). The following events occurred during week 1: • Actual demand during week 1 was 25 units. • Marketing forecasted that 40 units would be needed for week 9. An order for 10 in week 2 was accepted. An order for 20 in week 4 was accepted. • An order for 6 in week 3 was accepted. • The MPS in week 1 was produced as planned. 40 20 40 20 50 10 10 b) Update the record below after rolling through time. Complete the second table on the left.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Problem 6 Part A:
Available to promise in period 4 = 50

Problem 6 Part B:
PAB in period 7 = 35

In part A, the only thing that you need to do is to calculate the ATP in periods 1,4,5, and 7.

In part B, remember that you are rolling through time. The part B solution spreadsheet starts with time period 2 and period 1 is now history. For the part B, you must capture all of the events that occurred during week 1. For example, I gave you that the beginning PAB is 45. If you had 20 in stock (from part A), you produced 50 as planned in period 1, and the actual demand for period 1 was 25, then the beginning PAB (your stock quantity) is 20+50-25=45. The forecast and MPS quantities will not change from part A to part B. After you accept each of the orders (simply add the new order quantities to the existing customer order quantities in the correct time bucket), you will then recalculate the PAB, and then recalculate the ATP.

On
Week
a) Smell Fresh
hand
1
2
Forecast
20
20
PAB
Customer Orders
Available to Promise
5
3
20
50
30
3222
4
5
6
7
8
Problem 6: Georgia Clay and Gravel was updating the MPS record for one of its products, Smell Fresh Cat Litter.
Partially-completed MPS time-phased record is given below.
20
30
30
30
30
30
Week
10
30
50
20
40
10
Item: Smell
Fresh
On
hand 1
2
3
4
5
6
7
8
MPS
MPS lot size=50
50
50
50
50
g|
Forecast
20
20
Orders
5
20 50
233
220
20 20 30 30 30 30 30
On
Week
b) Smell Fresh
hand
2
3
4
5
6
7
8
9
Forecast
Customer Orders
PAB
Available to Promise
MPS
MPS lot size=50
45
Projected available
balance
Available-to-promise
MPS
MPS Lot Size = 50.
50
10 30 50
50 50
a) Complete the MPS time-phased record (the first table on the left).
The following events occurred during week 1:
• Actual demand during week 1 was 25 units.
• Marketing forecasted that 40 units would be needed for week 9.
An order for 10 in week 2 was accepted.
An order for 20 in week 4 was accepted.
• An order for 6 in week 3 was accepted.
• The MPS in week 1 was produced as planned.
40
20
40
20
50
10
10
b) Update the record below after rolling through time. Complete the second table on the left.
Transcribed Image Text:On Week a) Smell Fresh hand 1 2 Forecast 20 20 PAB Customer Orders Available to Promise 5 3 20 50 30 3222 4 5 6 7 8 Problem 6: Georgia Clay and Gravel was updating the MPS record for one of its products, Smell Fresh Cat Litter. Partially-completed MPS time-phased record is given below. 20 30 30 30 30 30 Week 10 30 50 20 40 10 Item: Smell Fresh On hand 1 2 3 4 5 6 7 8 MPS MPS lot size=50 50 50 50 50 g| Forecast 20 20 Orders 5 20 50 233 220 20 20 30 30 30 30 30 On Week b) Smell Fresh hand 2 3 4 5 6 7 8 9 Forecast Customer Orders PAB Available to Promise MPS MPS lot size=50 45 Projected available balance Available-to-promise MPS MPS Lot Size = 50. 50 10 30 50 50 50 a) Complete the MPS time-phased record (the first table on the left). The following events occurred during week 1: • Actual demand during week 1 was 25 units. • Marketing forecasted that 40 units would be needed for week 9. An order for 10 in week 2 was accepted. An order for 20 in week 4 was accepted. • An order for 6 in week 3 was accepted. • The MPS in week 1 was produced as planned. 40 20 40 20 50 10 10 b) Update the record below after rolling through time. Complete the second table on the left.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.