or Module 4:

Financial Reporting, Financial Statement Analysis and Valuation
8th Edition
ISBN:9781285190907
Author:James M. Wahlen, Stephen P. Baginski, Mark Bradshaw
Publisher:James M. Wahlen, Stephen P. Baginski, Mark Bradshaw
Chapter8: Investing Activities
Section: Chapter Questions
Problem 2QE
icon
Related questions
Question
Questionn.
Answer the following questions with regard to the AIA A201TM - General
Conditions of the Contract for Construction, a required reading item for Module 4:
a). An abandoned well was found in the area of a proposed footing, and the well
cap was clearly visible. The contractor claimed additional costs for structural fill.
Should the architect approve his claim?
b). Does the owner have the right to subcontract out portions of the work directly?
c). The building official pointed out that the lack of fire alarms in the project
violated local building codes. The owner went after the electrical contractor for
negligence in reviewing the drawings. Should the electrical contractor be
responsible for the delay and additional cost in fixing this problem?
d). How can the contractor check on the owner's financial strength?
e). In the contract, the stipulated allowance for the carpet is $10,000. The
contractor spent $9,500 (delivery and tax included) on purchasing the carpet
chosen by the owner and $1,000 on installation. This project specifies 10% for
overhead and profit markup for change orders. How much adjustment is the
contractor entitled to for this allowance item?
f). Why is it important to identify the owner's representative in writing?
g). The contractor encountered materially different site conditions during
excavation. In order to make a claim for additional costs, when does he have to file
the claim?
h). Does the owner have the right to reject a general contractor's (GC's)
subcontractor who is reasonably capable of performing the work?
Transcribed Image Text:Questionn. Answer the following questions with regard to the AIA A201TM - General Conditions of the Contract for Construction, a required reading item for Module 4: a). An abandoned well was found in the area of a proposed footing, and the well cap was clearly visible. The contractor claimed additional costs for structural fill. Should the architect approve his claim? b). Does the owner have the right to subcontract out portions of the work directly? c). The building official pointed out that the lack of fire alarms in the project violated local building codes. The owner went after the electrical contractor for negligence in reviewing the drawings. Should the electrical contractor be responsible for the delay and additional cost in fixing this problem? d). How can the contractor check on the owner's financial strength? e). In the contract, the stipulated allowance for the carpet is $10,000. The contractor spent $9,500 (delivery and tax included) on purchasing the carpet chosen by the owner and $1,000 on installation. This project specifies 10% for overhead and profit markup for change orders. How much adjustment is the contractor entitled to for this allowance item? f). Why is it important to identify the owner's representative in writing? g). The contractor encountered materially different site conditions during excavation. In order to make a claim for additional costs, when does he have to file the claim? h). Does the owner have the right to reject a general contractor's (GC's) subcontractor who is reasonably capable of performing the work?
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Financial Reporting, Financial Statement Analysis…
Financial Reporting, Financial Statement Analysis…
Finance
ISBN:
9781285190907
Author:
James M. Wahlen, Stephen P. Baginski, Mark Bradshaw
Publisher:
Cengage Learning