Please answer d, e and f only. Thanks
Q: Draw activity network of the project. Crash the activities step by step until all paths are critical
A: Project crashing is a process which helps to reduce the total completion time using additional costs…
Q: three important professional workplace expectations. and What disciplinary action is appropriate…
A: Important professional workplace expectation: 1) correspondence 2) How could I should act? 3)…
Q: QUESTION 29 Which of the following is not a "supply option" for sales & operations planning? A.…
A: Adjusting price:- Making the adjustments / changes in the pricing is not the task of the operations…
Q: (a) Formulate the problem as a linear program to detemnine the recipe of the bread to minimiz the…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: Required to prepare the action plan for the events show in table below and determine the Total Float…
A: Based on the Predecessor relationships given (the 2nd column of the tables show the predecessors of…
Q: Two recent graduates have decided to enter the field of microcomputers. They intend to manufacture…
A: Objective Functions and Constraints: Based on the given details, the objective…
Q: a. Develop a network representation of this problem. b. Develop a linear programming model that can…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: Explain the meaning of the Following concepts. 1. Brand- 2. Product Branding - 3. Brand Name- 4.…
A: 1) Brand A brand is a sign of identity, label, emblem, name, term, and/or sentence used by…
Q: What are employee affinity groups? How are they helpful within an organization?
A: An employee is an integral part of any organization. There are different aspects to an employee's…
Q: determine the time between orders in working days.
A: EOQ stands for economic order quantity. It is a company's optimal order quantity that undervalues…
Q: Q#2: What is Pareto chart, why it is use, need example? Q#3: What is fish bone diagram, why and…
A: Pareto charts are one of the most useful, versatile, and effective visualization tools out there.…
Q: Given the optimal number of reservations, what is the probability that you won't need to deal with…
A: The probability that there are no bumped passengers =The probability that the no shows the…
Q: a limited liability ement, the memb the withdrawal.
A: In Violation of the operating Agreement
Q: NCY Corp has an annual usage ( of 5,000 units. The ordering cost is RM 200 per order while the…
A: Economic order quantity is the optimal order quantity that company should purchase to minimise their…
Q: How does revenue management impact an aggregate plan?
A: The revenue management process can be broken down into two components: aggregate planning and price…
Q: The Administration of the Uconn school of Business must plan the school’s course offerings for the…
A: Objective Functions and Constraints: Based on the given details, the objective…
Q: What are some methods for increasing the efficiency of service delivery?
A: Providing great customer service is integral to the success of any business, no matter what industry…
Q: Which data source is most likely to provide reliable data? Question 3 options: An…
A: Answer: Option CA review by a consumer group..
Q: What exactly is meant by the term "Service Process Structuring"
A: The term service process structuring is determined by understanding the degree of customers…
Q: For the EOQ policy, the total annual stocking cost (the sum of the holding and ordering costs) for…
A: EOQ tells the optimal quantity to be ordered each time so that the cost is minimised.
Q: Identify the critical path. (Write the letters without spaces and commas.) Determine the number of…
A: A slack value indicating the available time in each activity to adjust without affecting the project…
Q: 1- Total project finishing time 2- Critical path, 3- Free float for each task. • 4- If Activity B is…
A: The critical path is the path with the longest duration.
Q: determine the minimum total annual inventory cost
A: Inventory cost is the cost covering the cost to order and the holding inventory. This cost is…
Q: DB sells 500 bottles of supplements per week at $ 75 per bottle. DB's supplier charges DB $ 20 per…
A: Inventory management is the process of planning, monitoring, and controlling the movement of…
Q: What problems arise in breaking the operation into elements? (Methods study)
A: Every business or organization exists to accomplish an objective. As such, it’s reasonable to assume…
Q: old, when her mother started sailing with her. Today, Monica is considering the possibility of…
A: According to the problem Monica considers accomplishment of the pilot study as 50-50 probability.
Q: Compilation of at least three trend in quantity food production.
A: Quality food production has become an important subject in recent years, with many social media…
Q: a) RDL Corporation has one small plant located on the outskirts of Manila. Its production is limited…
A: Objective Functions and Constraints: Based on the given details, the objective…
Q: "In conclusion, I congratulate the country upon the fraternal spirit of the people and the…
A: The question is related meaning of Manifestation
Q: Padilla Electronics stocks and sells a particular brand of microcomputer. It costs the firm $450…
A: Economic order quantity is the quantity of a product that is ordered from a supplier at one time. It…
Q: For what purpose are we concerned in identifying and evaluating potential threats?
A: Potential threats can be anything that can harm a business. Threats are the cause of any type of…
Q: Please provide definitions for the following expressions in the context of formal meetings:…
A: A formal meeting is an assembly of two or more people to take decision or action. The meeting takes…
Q: Suppose that you are given a decision situation with three possible states of nature: 5₁, 5₂, and…
A: Find the Given details below: Given details: Prior Probabilities P(s1) 0.5 P(s2) 0.3…
Q: Monica Britt has enjoyed sailing small boats since she was 7 years old, when her mother started…
A: From the given write-up, the following information can be extracted. States of nature…
Q: c) Jay Calahi is to supply gravel for projects located in three different sites. He has three…
A: Find the Given details below: Given details: Cost per Truckload (p) From/To A B C…
Q: How many units of Item X should be ordered each time? O 94 units O 95 units 100 units O O
A: EOQ stands for economic order quantity. It is a company's optimal order quantity that undervalues…
Q: plain the parts of project proposal 1. The title 2. Project Proponents 3. Implementing units 4.…
A: Important parts of project proposal 1) The title 2) Project Proponents 3) Implementing units 4)…
Q: Despite companies engaging foreign agents and distributors in their distribution channel,…
A: While it is not required by Ghanaian law to do so (usually speaking), the US Business Service does…
Q: For the EOQ policy, the total annual stocking cost (the sum of the holding and ordering costs) for…
A: Total cost = annual holding cost + annual ordering cost
Q: Production facilities include the factory, production machines and tooling, material handling…
A: Production systems may be described as transformation processes, processes that convert resources…
Q: Why do you think making progress in meaningful work ranks as the most important factor contributing…
A: Motivation depicts the ambitions, desires, drives, requirements, and wants which elucidate employees…
Q: Table 1 shows two budget forecasts F1 and F2 for a project. The project contains a set of activity A…
A: Formulae used: Error = Actual data - Forecast data RSFE = Cumulative sum of forecast error MAD…
Q: a) Develop a network diagram for the project. Identify the critical path. b) If the company would…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: Explain what are the benefits of the obligations of business actors (CSR) in implementing…
A: CSR means corporate social responsibility, and it is the way businesses take into account the social…
Q: The Total Manufacturing costs incurred for the month was $620,525. Beginning work in process was…
A: The question is related to cost of goods manufactured in Production management. The Cost of Goods…
Q: 1. What is the optimal number of motors that Phillips's managers should order according to the E0Q…
A: EOQ stands for economic order quantity. It is a company's optimal order quantity that undervalues…
Q: PM.66 Real estate developer Russell Call was working with a few contractors to make a number of…
A: Project crashing is a process which reduces the total duration of the project using additional costs…
Q: Define and briefly discuss the concept of labour relations. In 10 bullet points
A: Labor relations refers to the process through which employers and employees, management, and unions…
Q: A car mechanic, Carlos, can install new mufflers at an average rate of 3 every hour (following an…
A: Note: - Since we can answer only up to three subparts we will answer the first three subparts(a, b,…
Q: A restaurant serves an average of 623 desert (leche flan) servings every week. The manager places…
A: The current order quantity =1000 servings, Average weekly demand=623 servings, Let me assume the…
Trending now
This is a popular solution!
Step by step
Solved in 5 steps with 4 images
- 8. Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 7 − E 4 B B 6 − F 5 B C 4 A G 11 C, E D 2 A H 8 D , F Part 2 Dave's earliest start (ES) and earliest finish (EF) are: Activity ES EF A ___ 7 Activity ES EF B ____ Activity ES EF C _____ Activity ES EF D ___ Activity ES EF E ___ Activity ES EF F __ Activity ES EF G ____…Describe the computation of mean activity times and activity variance in probabilistic CPM/PERT analysis. 2. Which method for determining activity time estimates, deterministic or probabilistic is preferable? Explain. 3. Explain how a Gantt chart differs from a CPM/PERT network. What advantages does CPM/PERT have? 4. Describe the limitations and disadvantages of CPM/PERT. 5. Identify and briefly describe the major elements of project management.Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 7 − E 4 B B 6 − F 5 B C 4 A G 10 C, E D 2 A H 8 D , F Part 2 Dave's earliest start (ES) and earliest finish (EF) are: Part 3 Part 4 Part 5 Part 6 Part 7 Part 8 Part 9 Part 10 Dave's latest start (LS) and latest finish (LF) are:…
- Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)A 6 - E 5 BB 8 - F 6 BC 2 A G 9 C, ED 3 A H 7 D , F Dave's earilest start (ES) and earliest finish (EF) are: Activity ES EF A 0 6 B 0 ? C D E F G HDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 7 − E 5 B B 8 − F 6 B C 4 A G 11 C, E D 3 A H 7 D , F Part 2 Dave's earliest start (ES) and earliest finish (EF) are: Part 3 Part 4 Part 5 Part 6 Part 7 Part 8 Part 9 Part 10 Dave's latest start (LS) and latest finish (LF) are:…A plumber has decided to use the techniques of project management in order to plan a job. He knew all the different activities of the job, their precedence and their average durations. They are shown on the table below. Activity Duration (days) Preceding activities A 3 None B 3 None C 4 A D 8 A E 2 B and C Required: 1. Draw a network diagram representing the sequence of activities and the dependence between them. 2. Determine how long it will take to complete the job by conducting the forward pass 3. By conducting the backward pass, identify the critical path and the non-critical path(s). Note: The work for this task should be produced using Word drawing facilities. The forward and backward passes should be clearly shown on the diagram. The calculations should be shown next to the network diagram.
- Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)A 7 - E 4 BB 8 - F 7 BC 4 A G 11 C, ED 1 A H 6 D , F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES EF A 0 7 B 0 8 C 7 11 D 7 88 E 8 12 Part 7 F ? ? G ? ? H ? ?To be able to meet delivery dates, a project consultant intimates that a project should be analyzed with activities as follows: ACTIVITY IMMEDIATE PREDECESSOR EXPECT DURATION (WEEKS) A. Initial discussion none 3 B. product design none 5 C. Market survey B 3 D. market evaluation A,C 4 E. product costing D 8 F. sales plan C 2 G. product pricing F 4 H. prototype F 2 I. master inform B 5 J.prototype testing HEG 3 (i) Draw a network to represent the various activities of the project.(ii) Draw up a table showing for each activity, the earliest and latest start and finish times and total float/slack.(iii) Determine the critical path and project duration.(iv) As a management science student, advise the management about the effect on the project completion time If the start time of activity A is delayed by 3weeks, activity G is delayed by 8 weeks1. For the following Activity table draw the CPM diagram Using Activity On Node. Show the ES, LS, EF, LF and Slack for each activity on the diagram. Indicate the Critical path. Activity Time (Days) Predecessor A 4 ------------ B 7 A C 8 A D 2…
- 3.1 Draw an Activity-On-Arrow (AOA) network diagram representing the project. Put the nodenumbers in circles and draw arrows from node to node, labelling each arrow with theactivity letter and estimated duration. 3.2 Identify all the paths on the network diagram and note how long they are. 3.3 What is the critical path for this project and how long is it? 3.4 What is the shortest possible time needed to complete the project?The Advanced Tech Company has a project to design anintegrated information database for a major bank. Datafor the project are given in Table 7.6. Indirect project costsamount to $300 per day. The company will incur a $150 perday penalty for each day the project lasts beyond day 14.a. What is the project’s duration if only normal times are used?b. What is the minimum-cost schedule?c. What is the critical path for the minimum-cost schedule?11-23 Tom Schriber, the director of personnel of Manage-ment Resources, Inc., is in the process of designing a program that its customers can use in the job-findingprocess. Some of the activities include preparingresumés, writing letters, making appointments to seeprospective employers, and researching companiesand industries. The information on these activities isshown in the following table: (d) Determine the critical path(s) and project com-pletion time. (e) Determine the probability that the project willbe finished in 70 days or less.(f) Determine the probability that the project willbe finished in 80 days or less.