Please help me solve (especially payback / discount payback)

Fundamentals of Financial Management (MindTap Course List)
15th Edition
ISBN:9781337395250
Author:Eugene F. Brigham, Joel F. Houston
Publisher:Eugene F. Brigham, Joel F. Houston
Chapter13: Real Options And Other Topics In Capital Budgeting
Section: Chapter Questions
Problem 2P: OPTIMAL CAPITAL BUDGET Marble Construction estimates that its WACC is 10% if equity comes from...
icon
Related questions
icon
Concept explainers
Question
Please help me solve (especially payback / discount payback)
 
Ch 11: End-of-Chapter Problems - The Basics of Capital Budgeting
A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows:
1
2
3
0
4
Project M $18,000 $6,000 $6,000 $6,000 $6,000 $6,000
Project N -$54,000 $16,800 $16,800 $16,800 $16,800 $16,800
a. Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations.
Project M
Project N
30000
84000
Calculate IRR for each project. Round your answers to two decimal places. Do not round your intermediate calculations.
Project M
19.86 %
Project N
Calculate MERR for each project. Round your answers to two decimal places. Do not round your intermediate calculations.
Project M
-1,99 %
Project N
Calculate payback for each project. Round your answers to two decimal places. Do not round your intermediate calculations.
Project M
years
Project N
years
Calculate discounted payback for each project. Round your answers to two decimal places. Do not round your intermediate calculations.
Project M
years
Project N
years
b. Assuming the projects are independent, which one(s) would you recommend?
Both projects would be accepted since both of their NPV's are positive.
If the projects are mutually exclusive, which would you recommend?
If the projects are mutually exclusive, the project with the highest positive NPV is chosen Accept Project N.
d. Notice that the projects have the same cash flow timing pattern. Why is there a conflict between NPV and IRRY
The conflict between NPV and IRR occurs due to the difference in the size of the projects.
Transcribed Image Text:Ch 11: End-of-Chapter Problems - The Basics of Capital Budgeting A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 1 2 3 0 4 Project M $18,000 $6,000 $6,000 $6,000 $6,000 $6,000 Project N -$54,000 $16,800 $16,800 $16,800 $16,800 $16,800 a. Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M Project N 30000 84000 Calculate IRR for each project. Round your answers to two decimal places. Do not round your intermediate calculations. Project M 19.86 % Project N Calculate MERR for each project. Round your answers to two decimal places. Do not round your intermediate calculations. Project M -1,99 % Project N Calculate payback for each project. Round your answers to two decimal places. Do not round your intermediate calculations. Project M years Project N years Calculate discounted payback for each project. Round your answers to two decimal places. Do not round your intermediate calculations. Project M years Project N years b. Assuming the projects are independent, which one(s) would you recommend? Both projects would be accepted since both of their NPV's are positive. If the projects are mutually exclusive, which would you recommend? If the projects are mutually exclusive, the project with the highest positive NPV is chosen Accept Project N. d. Notice that the projects have the same cash flow timing pattern. Why is there a conflict between NPV and IRRY The conflict between NPV and IRR occurs due to the difference in the size of the projects.
Expert Solution
steps

Step by step

Solved in 3 steps with 6 images

Blurred answer
Knowledge Booster
Dividend Policy
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Fundamentals of Financial Management (MindTap Cou…
Fundamentals of Financial Management (MindTap Cou…
Finance
ISBN:
9781337395250
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
Fundamentals of Financial Management (MindTap Cou…
Fundamentals of Financial Management (MindTap Cou…
Finance
ISBN:
9781285867977
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
Fundamentals of Financial Management, Concise Edi…
Fundamentals of Financial Management, Concise Edi…
Finance
ISBN:
9781305635937
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
Fundamentals of Financial Management, Concise Edi…
Fundamentals of Financial Management, Concise Edi…
Finance
ISBN:
9781285065137
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
Fundamentals Of Financial Management, Concise Edi…
Fundamentals Of Financial Management, Concise Edi…
Finance
ISBN:
9781337902571
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
EBK CFIN
EBK CFIN
Finance
ISBN:
9781337671743
Author:
BESLEY
Publisher:
CENGAGE LEARNING - CONSIGNMENT