Prepare schedules to compute the amount of gross profit to be recognized for the year ended December 31, 2025, and the amount to be shown as "costs and recognized profit in excess of billings" or "billings in excess of costs and recognized profit" at December 31, 2025, under each of the following methods. (Enter negative amounts using either a negative sign preceding the number eg.-45 or parentheses eg. (45). If answer is O, please enter O. Do not leave any fields blank.) (a) Cost-recovery method. Gross profit to be recognized $

SWFT Comprehensive Vol 2020
43rd Edition
ISBN:9780357391723
Author:Maloney
Publisher:Maloney
Chapter16: Accounting Periods And Methods
Section: Chapter Questions
Problem 41P
icon
Related questions
icon
Concept explainers
Topic Video
Question
Oriole Construction Company began operations on January 1, 2025. During the year, Oriole Construction entered into a contract with
Winds Corp. to construct a manufacturing facility. At that time, Oriole estimated that it would take 5 years to complete the facility at a
total cost of $4.484,000. The total contract price for construction of the facility is $5,972,000. During the year, Oriole incurred
$1,082,400 in construction costs related to the construction project. The estimated cost to complete the contract is $4,329,600.
Winds Corp. was billed and paid 25% of the contract price.
(a)
Prepare schedules to compute the amount of gross profit to be recognized for the year ended December 31, 2025, and the
amount to be shown as "costs and recognized profit in excess of billings" or "billings in excess of costs and recognized profit" at
December 31, 2025, under each of the following methods. (Enter negative amounts using either a negative sign preceding the number
eg.-45 or parentheses e.g. (45). If answer is O, please enter O. Do not leave any fields blank.)
(a) Cost-recovery method.
Gross profit to be recognized
ORIOLE CONSTRUCTION COMPANY
Computation of Billings on Uncompleted Contract in Excess of
Related Costs under Cost-Recovery Method
LA
Transcribed Image Text:Oriole Construction Company began operations on January 1, 2025. During the year, Oriole Construction entered into a contract with Winds Corp. to construct a manufacturing facility. At that time, Oriole estimated that it would take 5 years to complete the facility at a total cost of $4.484,000. The total contract price for construction of the facility is $5,972,000. During the year, Oriole incurred $1,082,400 in construction costs related to the construction project. The estimated cost to complete the contract is $4,329,600. Winds Corp. was billed and paid 25% of the contract price. (a) Prepare schedules to compute the amount of gross profit to be recognized for the year ended December 31, 2025, and the amount to be shown as "costs and recognized profit in excess of billings" or "billings in excess of costs and recognized profit" at December 31, 2025, under each of the following methods. (Enter negative amounts using either a negative sign preceding the number eg.-45 or parentheses e.g. (45). If answer is O, please enter O. Do not leave any fields blank.) (a) Cost-recovery method. Gross profit to be recognized ORIOLE CONSTRUCTION COMPANY Computation of Billings on Uncompleted Contract in Excess of Related Costs under Cost-Recovery Method LA
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
Financial Statements
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
SWFT Comprehensive Vol 2020
SWFT Comprehensive Vol 2020
Accounting
ISBN:
9780357391723
Author:
Maloney
Publisher:
Cengage
SWFT Comprehensive Volume 2019
SWFT Comprehensive Volume 2019
Accounting
ISBN:
9780357233306
Author:
Maloney
Publisher:
Cengage
SWFT Individual Income Taxes
SWFT Individual Income Taxes
Accounting
ISBN:
9780357391365
Author:
YOUNG
Publisher:
Cengage
Individual Income Taxes
Individual Income Taxes
Accounting
ISBN:
9780357109731
Author:
Hoffman
Publisher:
CENGAGE LEARNING - CONSIGNMENT
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
CONCEPTS IN FED.TAX., 2020-W/ACCESS
CONCEPTS IN FED.TAX., 2020-W/ACCESS
Accounting
ISBN:
9780357110362
Author:
Murphy
Publisher:
CENGAGE L