Read the case study entitled “Hudsonbanc Billing System Upgrade” below. Two regional banks with similar geographic territories merged to form HudsonBanc. Both banks had credit card operations and operated billing systems that had been internally developed and upgraded over three decades. The systems performed similar functions, and both operated primarily in batch mode on mainframe computers. Merging the two billing systems was identified as a high-priority cost-saving measure. HudsonBanc initiated a project to investigate how to merge the two billing systems. Upgrading either system was quickly ruled out because the existing technology was considered old, and the costs of upgrading the system were estimated to be too high. HudsonBanc decided that a new component-based, Web-oriented system should be built or purchased. Management preferred the purchase option because it was assumed that a purchased system could be brought online more quickly and cheaply. An RFP (request for proposal) was prepared, many responses were received, and after months of business modeling and requirements activities, a vendor was chosen. Hardware for the new system was installed in early January. The software was installed the following week, and a random sample of 10 percent of the customer accounts was copied to the new system. The new system was operated in parallel with the old systems for two months. To save costs involved with complete duplication, the new system computed but didn’t print billing statements. Payments were entered into both systems and used to update parallel customer account databases. Duplicate account records were checked manually to ensure that they were the same. After the second test billing cycle, the new system was declared ready for operation. All customer accounts were migrated to the new system in mid-April. The old systems were turned off on May 1, and the new system took over the operation. Problems occurred almost immediately. The system was unable to handle the greatly increased volume of transactions. Data entry and customer Web access slowed to a crawl, and payments were soon backed up by several weeks. The system wasn’t handling certain types of transactions correctly (e.g., charge corrections and credits for overpayment). Manual inspection of the recently migrated account records showed errors in approximately 50,000 accounts. It took almost six weeks to adjust the incorrect accounts and update functions to handle all transaction types correctly. On June 20, the company attempted to print billing statements for the 50,000 corrected customer accounts. The system refused to print any information for transactions more than 30 days old. A panicked consultation with the vendor concluded that fixing the 30-day restriction would require more than a month of work and testing. It was also concluded that manual entry of account adjustments followed by billing within 30 days was the fastest and least risky way to solve the immediate problem. Clearing the backlog took two months. During that time, many incorrect bills were mailed. Customer support telephone lines were continually overloaded. Twenty-five people were reassigned from other operational areas, and additional phone lines were added to provide sufficient customer support capacity. System development personnel were reassigned to IS operations for up to three months to assist in clearing the billing backlog. Federal and state regulatory authorities stepped in to investigate the problems. HudsonBanc agreed to allow customers to spread payments for late bills over three months without interest charges. Setting up the payment arrangements further aggravated the backlog and staffing problems. questions a. What type of installation did HudsonBanc use for its new system? Was it an appropriate choice? b. How could the operational problems have been avoided?

Fundamentals of Information Systems
9th Edition
ISBN:9781337097536
Author:Ralph Stair, George Reynolds
Publisher:Ralph Stair, George Reynolds
Chapter8: System Acquisition And Development
Section: Chapter Questions
Problem 1.1CS: It is perhaps not surprising that Etsy was an early adopter of DevOps. It is a relatively small...
icon
Related questions
Question
100%

Read the case study entitled “Hudsonbanc Billing System Upgrade” below.
Two regional banks with similar geographic territories merged to form HudsonBanc. Both banks
had credit card operations and operated billing systems that had been internally developed and
upgraded over three decades. The systems performed similar functions, and both operated
primarily in batch mode on mainframe computers. Merging the two billing systems was identified
as a high-priority cost-saving measure. HudsonBanc initiated a project to investigate how to
merge the two billing systems. Upgrading either system was quickly ruled out because the
existing technology was considered old, and the costs of upgrading the system were estimated
to be too high. HudsonBanc decided that a new component-based, Web-oriented system should
be built or purchased. Management preferred the purchase option because it was assumed that
a purchased system could be brought online more quickly and cheaply. An RFP (request for
proposal) was prepared, many responses were received, and after months of business modeling
and requirements activities, a vendor was chosen. Hardware for the new system was installed
in early January. The software was installed the following week, and a random sample of 10
percent of the customer accounts was copied to the new system. The new system was operated
in parallel with the old systems for two months. To save costs involved with complete duplication,
the new system computed but didn’t print billing statements. Payments were entered into both
systems and used to update parallel customer account databases. Duplicate account records
were checked manually to ensure that they were the same. After the second test billing cycle,
the new system was declared ready for operation. All customer accounts were migrated to the
new system in mid-April. The old systems were turned off on May 1, and the new system took
over the operation. Problems occurred almost immediately. The system was unable to handle
the greatly increased volume of transactions. Data entry and customer Web access slowed to a
crawl, and payments were soon backed up by several weeks. The system wasn’t handling
certain types of transactions correctly (e.g., charge corrections and credits for overpayment).
Manual inspection of the recently migrated account records showed errors in approximately
50,000 accounts. It took almost six weeks to adjust the incorrect accounts and update functions
to handle all transaction types correctly. On June 20, the company attempted to print billing
statements for the 50,000 corrected customer accounts. The system refused to print any
information for transactions more than 30 days old. A panicked consultation with the vendor
concluded that fixing the 30-day restriction would require more than a month of work and testing.
It was also concluded that manual entry of account adjustments followed by billing within 30
days was the fastest and least risky way to solve the immediate problem. Clearing the backlog
took two months. During that time, many incorrect bills were mailed. Customer support
telephone lines were continually overloaded. Twenty-five people were reassigned from other
operational areas, and additional phone lines were added to provide sufficient customer support
capacity. System development personnel were reassigned to IS operations for up to three
months to assist in clearing the billing backlog. Federal and state regulatory authorities stepped
in to investigate the problems. HudsonBanc agreed to allow customers to spread payments for
late bills over three months without interest charges. Setting up the payment arrangements
further aggravated the backlog and staffing problems.

questions

a. What type of installation did HudsonBanc use for its new system? Was it an appropriate
choice?
b. How could the operational problems have been avoided?

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
NextGen Implementation
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals of Information Systems
Fundamentals of Information Systems
Computer Science
ISBN:
9781337097536
Author:
Ralph Stair, George Reynolds
Publisher:
Cengage Learning
Principles of Information Systems (MindTap Course…
Principles of Information Systems (MindTap Course…
Computer Science
ISBN:
9781305971776
Author:
Ralph Stair, George Reynolds
Publisher:
Cengage Learning