Required information [The following information applies to the questions displayed below] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026 Information related to the contract is as follows: Cost incurred during the year 2024 2025 2026 Estimated costs to complete as of year-end $ 2,016,000 5,184,000 Billings during the year 2,180,000 $ 2,808,000 2,376,000 2,644,000 $ 2,613,600 0 Cash collections during the year 1,890,000 2,500,000 5,176,000 5,610,000 Westgate recognizes revenue over time according to percentage of completion. 4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs Incurred and costs to complete information. Note: Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign. Costs incurred during the year Estimated costs to complete as of year-end 2024 2025 2026 Revenue $ 2,800,000 Gross profit (loss) $ 784,000 2024 $ 2,016,000 5,184,000 2025 $ 3,890,000 3,190,000 2026 $ 3,290,000 0
Required information [The following information applies to the questions displayed below] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026 Information related to the contract is as follows: Cost incurred during the year 2024 2025 2026 Estimated costs to complete as of year-end $ 2,016,000 5,184,000 Billings during the year 2,180,000 $ 2,808,000 2,376,000 2,644,000 $ 2,613,600 0 Cash collections during the year 1,890,000 2,500,000 5,176,000 5,610,000 Westgate recognizes revenue over time according to percentage of completion. 4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs Incurred and costs to complete information. Note: Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign. Costs incurred during the year Estimated costs to complete as of year-end 2024 2025 2026 Revenue $ 2,800,000 Gross profit (loss) $ 784,000 2024 $ 2,016,000 5,184,000 2025 $ 3,890,000 3,190,000 2026 $ 3,290,000 0
Chapter3: Income Sources
Section: Chapter Questions
Problem 88P
Related questions
Question
A9
![Required information
[The following information applies to the questions displayed below]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2026 Information related to the contract is as follows:
Cost incurred during the year
2024
2025
2026
Estimated costs to complete as of year-end
$ 2,016,000
5,184,000
Billings during the year
2,180,000
$ 2,808,000
2,376,000
2,644,000
$ 2,613,600
0
Cash collections during the year
1,890,000
2,500,000
5,176,000
5,610,000
Westgate recognizes revenue over time according to percentage of completion.
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs
Incurred and costs to complete information.
Note: Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts
should be indicated with a minus sign.
Costs incurred during the year
Estimated costs to complete as of year-end
2024
2025
2026
Revenue
$
2,800,000
Gross profit (loss)
$
784,000
2024
$ 2,016,000
5,184,000
2025
$ 3,890,000
3,190,000
2026
$ 3,290,000
0](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F1ed3915b-403d-4625-bb4a-0ea5a5248ccc%2F5dbf3383-a8a1-4045-a21b-3ad06e3e35c1%2F9v0g1eo_processed.png&w=3840&q=75)
Transcribed Image Text:Required information
[The following information applies to the questions displayed below]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2026 Information related to the contract is as follows:
Cost incurred during the year
2024
2025
2026
Estimated costs to complete as of year-end
$ 2,016,000
5,184,000
Billings during the year
2,180,000
$ 2,808,000
2,376,000
2,644,000
$ 2,613,600
0
Cash collections during the year
1,890,000
2,500,000
5,176,000
5,610,000
Westgate recognizes revenue over time according to percentage of completion.
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs
Incurred and costs to complete information.
Note: Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts
should be indicated with a minus sign.
Costs incurred during the year
Estimated costs to complete as of year-end
2024
2025
2026
Revenue
$
2,800,000
Gross profit (loss)
$
784,000
2024
$ 2,016,000
5,184,000
2025
$ 3,890,000
3,190,000
2026
$ 3,290,000
0
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 1 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you