Smooth Chin Device Company The Smooth Chin Device Company is a manufacturer of high-­-end electric razors. These razors are produced using a machine-­-paced process. For each razor, a tray with components enters the process at the beginning of a conveyor belt. The tray then passes through the six steps (consisting of various tasks) explained in the table below. Workers perform the assembly operations on the moving tray. The last step consists of an inspection of the then fully assembled razor. The activity times of the process are as follows: Station Tasks A Preparation 1. Lay out chassis [12 sec] 2. Lay out screws [15 sec] 3. Lay out all other components [17 sec] Total time for A: 44 sec B Assembly   4. Perform task AS1 [10 sec] 5. Perform task AS2 [10 sec] 6. Perform task AS3 [20 sec] Total time for B: 40 sec C Assembly   7. Perform task AS4 [14 sec] 8. Perform task AS5 [16 sec] 9. Perform task AS6 [20 sec] 10. Perform task AS7 [5 sec] Total time for C: 55 sec D Assembly   11. Perform task AS8 [30 sec] 12. Perform task AS9 [30 sec] Total time for D: 60 sec E Assembly   13. Perform task AS10 [11 sec] 14. Perform task AS11 [19 sec] 15. Perform task AS12 [20 sec] Total time for E: 50 sec F Inspection 16. Inspect electrics [20 sec] 17. Inspect aesthetics [20 sec] Total time for F: 40 sec     There are six workers, one at each of the six stations (A-­-F). They begin their workday at 8:00 am and work steadily until 4:00 pm. (They are replaced with other workers for breaks and lunches, 2 but the production is not slowed or stopped during these times.) Their hourly wage rate is $25 per hour. For the first five questions, you can assume unlimited demand.   SC1. Which station is the bottleneck of the process? SC2. What is the process capacity (you can ignore any start-­-up or empty system effects), in razors/hour? SC3. What are the direct labor costs (you can ignore any start-­-up or empty system effects) associated with producing one razor, in dollars? SC4. What is the average labor utilization of the six workers?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question

Smooth Chin Device Company

The Smooth Chin Device Company is a manufacturer of high-­-end electric razors. These razors are produced using a machine-­-paced process. For each razor, a tray with components enters the process at the beginning of a conveyor belt. The tray then passes through the six steps (consisting of various tasks) explained in the table below. Workers perform the assembly operations on the moving tray. The last step consists of an inspection of the then fully assembled razor. The activity times of the process are as follows:

Station

Tasks

A

Preparation

1. Lay out chassis [12 sec]

2. Lay out screws [15 sec]

3. Lay out all other components [17 sec]

Total time for A: 44 sec

B

Assembly

 

4. Perform task AS1 [10 sec]

5. Perform task AS2 [10 sec]

6. Perform task AS3 [20 sec]

Total time for B: 40 sec

C

Assembly

 

7. Perform task AS4 [14 sec]

8. Perform task AS5 [16 sec]

9. Perform task AS6 [20 sec]

10. Perform task AS7 [5 sec]

Total time for C: 55 sec

D

Assembly

 

11. Perform task AS8 [30 sec]

12. Perform task AS9 [30 sec]

Total time for D: 60 sec

E

Assembly

 

13. Perform task AS10 [11 sec]

14. Perform task AS11 [19 sec]

15. Perform task AS12 [20 sec]

Total time for E: 50 sec

F

Inspection

16. Inspect electrics [20 sec]

17. Inspect aesthetics [20 sec]

Total time for F: 40 sec

 

 

There are six workers, one at each of the six stations (A-­-F). They begin their workday at 8:00 am and work steadily until 4:00 pm. (They are replaced with other workers for breaks and lunches, 2 but the production is not slowed or stopped during these times.) Their hourly wage rate is $25 per hour. For the first five questions, you can assume unlimited demand.

 

SC1. Which station is the bottleneck of the process?

SC2. What is the process capacity (you can ignore any start-­-up or empty system effects), in razors/hour?

SC3. What are the direct labor costs (you can ignore any start-­-up or empty system effects) associated with producing one razor, in dollars?

SC4. What is the average labor utilization of the six workers?

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Follow-up Questions
Read through expert solutions to related follow-up questions below.
Follow-up Question
There are six workers, one at each of the six stations (A-F). They begin their workday at 8:00a.m. and work steadily
until 4:00 pm. (They are replaced with other workers for breaks and lunches, but the production is not slowed or
stopped during these times.) Their hourly wage rate is $25 per hour. You can assume unlimited demand.
What is the average labor utilization (you can ignore any start-up or empty system effects) of the six workers?
Please give your answer in decimal form (e.g. 0.5 for 50% utilization).
Transcribed Image Text:There are six workers, one at each of the six stations (A-F). They begin their workday at 8:00a.m. and work steadily until 4:00 pm. (They are replaced with other workers for breaks and lunches, but the production is not slowed or stopped during these times.) Their hourly wage rate is $25 per hour. You can assume unlimited demand. What is the average labor utilization (you can ignore any start-up or empty system effects) of the six workers? Please give your answer in decimal form (e.g. 0.5 for 50% utilization).
Solution
Bartleby Expert
SEE SOLUTION
Knowledge Booster
Lean manufacturing
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,